Will County Receives Detailed Update on Landfill Expansion Investigation

Spread the love

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Today Jun 11
Sunny
80° 60°

Sunny

💨 15 mph 💧 0%

Leave a Comment





Latest News Stories

WATCH: Justice Kennedy talks about 'Life, Law & Liberty'

WATCH: Justice Kennedy talks about ‘Life, Law & Liberty’

By Dave MasonThe Center Square It’s important to understand what the framers of the U.S. Constitution wrote and intended, but the U.S. Supreme Court’s work goes beyond that, according to...
WA congressman urges Senate to confirm Trump DOJ nominee ahead of Dec. 4 deadline

WA congressman urges Senate to confirm Trump DOJ nominee ahead of Dec. 4 deadline

By Tim ClouserThe Center Square U.S. Rep. Michael Baumgartner, R-Wash., sent a letter on Wednesday urging the Senate to confirm Pete Serrano as U.S. attorney for the Eastern District of...
Judge who blocked Trump was major Democrat player as trial lawyer

Judge who blocked Trump was major Democrat player as trial lawyer

By Daniel Fisher | Legal NewslineThe Center Square The federal judge who ordered President Trump to continue paying food-stamp benefits owes his fortune to cigarettes and Democratic political ties forged...
Arizona recommends measles vaccine during outbreak

Arizona recommends measles vaccine during outbreak

By Chris WoodwardThe Center Square Arizona is recommending vaccinations to combat the state's worst measles outbreak since the 1990s. The latest update this week showed the state has 111 cases...
Govt. shutdown leads to over 800 flights cancelled, number growing

Govt. shutdown leads to over 800 flights cancelled, number growing

By Thérèse BoudreauxThe Center Square As the government shutdown drags into its 38th day and forced flight reductions begin taking effect, the number of daily flight cancellations Americans are experiencing...
Illinois approves $1.5B transit package, funding for long-delayed projects

Illinois approves $1.5B transit package, funding for long-delayed projects

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois lawmakers approved a $1.5 billion transit package, including long-delayed Moline-to-Chicago rail, hailed by Democrats as...
Joliet-Junior-college.-Graphic-Logo.5

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Supreme Court allows Trump to withhold partial SNAP payment

Supreme Court allows Trump to withhold partial SNAP payment

By Brett RowlandThe Center Square The Supreme Court said Friday that the Trump administration could withhold a partial payment for the federal food benefits program amid the longest-ever government shutdown....
Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor's proposal would hinder employment;

Illinois quick hits: State EPA looks to fund EV charging stations; Tax Foundation says mayor’s proposal would hinder employment;

By Jim Talamonti | The Center SquareThe Center Square State EPA looks to fund EV charging stations The Illinois Environmental Protection Agency (EPA) has announced an Electric Vehicle (EV) Charging...
Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
Screenshot 2025-11-05 at 3.38.44 PM

Frankfort Board Approves Final Plats for Crystal Brook and Copper Creek Subdivisions

Frankfort Village Board Meeting | November 3, 2025 Article Summary: The Frankfort Village Board approved final plats for two major residential developments on Monday, November 3, 2025, advancing plans for...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...