Future regional power supply down, but not out

Future regional power supply down, but not out

Spread the love

(The Center Square) – Shrinking power supply remains a challenge according to the grid operator’s most recent capacity auction, signaling that regional utility bills could still climb, albeit more slowly, as demand for electricity grows faster than can be provided.

PJM, the organization tasked with managing the flow of power for 67 million people across 13 states and Washington, D.C., collects annual bids from generators that commit them to providing energy supply over the following 12 months. In this case, it’s for the 2028-29 operating year.

By doing so, the organization can better hedge against blackouts and soaring prices that could happen if there’s not enough power to turn on furnaces in the dead of winter or air conditioning at the height of summer.

“These auction results show that demand for electricity continues to grow faster than electricity supply,” said David Mills, PJM president and CEO. “At the same time, PJM recognizes how this supply-and-demand imbalance impacts the reliability of the system and costs for consumers. We are working with government and industry leaders on multiple fronts to restore that balance by bringing on new generation as fast as possible and managing the growth of new load on the grid.”

But a better solution, according to energy producers, state officials, and PJM alike, would be to plug more supply into the grid, which can help limit the stress fractures anticipated from the data center boom.

Auction Price

Results of PJM’s 2028-2029 Base Residual Auction show the price reached the federally approved cap of $325 per MW-day throughout the PJM region – 2.5% below the $333.44 price in the previous auction.

The auction’s cleared capacity totaled $16.4 billion. PJM notes that figure does not represent the total cost to customers because some utilities and other load-serving entities secure capacity through self-supply arrangements or bilateral contracts and are not subject to the auction clearing price.

Katie Blume, coalition chair of Clean Power PA, said the results amounted to “more of the same: high prices driven by surging data center demand, and a grid that’s getting less reliable, not more.”

Blume credited the price cap negotiated by Gov. Josh Shapiro with preventing steeper increases, saying it has saved consumers nearly $13 billion over two auctions. However, she said a cap does not add new power supplies or resolve PJM’s underlying problems.

She called for making data centers pay their “fair share” of grid costs and accelerating the connection of wind, solar, and battery-storage projects.

Reliability Shortfall

For the second consecutive auction, PJM secured less capacity than required to meet its reliability target. The 2028-2029 auction fell short by 6,831 MW, leaving the grid below the reserve cushion required to meet a one-in-10-year reliability standard.

A rough estimate puts the total number of homes powered by that many megawatts around 5.5 million. This figure assumes PJM’s standard of 1 MW is equal to supplying an average of 800 homes.

The organization, however, said that the shortfall does not necessarily mean the system will be unable to meet demand. It means the grid will operate with slimmer reserves and greater risk during extreme conditions. It continues to hold a reserve margin of 14.7%.

The shortfall was not unexpected given the trend. The previous auction fell approximately 6,500 MW short, and large load projects continue to be added to the demand forecast.

Forecast peak demand for 2028-2029 is approximately 2,000 MW higher than in the previous delivery year.

Supply and Proposed Solutions

The auction secured 138,318 MW of capacity, an increase of 3,733 MW from the previous auction. That included 525 MW from new generation and upgrades to existing plants.

That’s enough supply to power 69 million and 138 million homes, dependent upon the season.

The committed resources include: 46% natural gas, 20% nuclear, 18% coal, 5% demand response, 4% hydro, 2% wind, 2% oil, and 1% solar.

PJM said it is working to increase supply and manage demand by clearing its project queue, creating a faster pathway for certain high-priority generation proposals, improving the performance of existing plants, and developing “Connect and Manage” frameworks that would allow data centers and other large users to connect under flexible operating conditions.

The grid operator also plans to seek federal approval for a Reliability Backstop Procurement intended to address near-term supply needs.

“All of these initiatives are critical to keeping the lights on while allowing states to protect their everyday electricity customers,” Mills said.

Electric Power Supply Association President and CEO Todd Snitchler said historically low capacity prices had discouraged investment in generation, while the higher prices that began with PJM’s July 2024 auction prompted companies to announce, restart, expand, or advance tens of gigawatts of projects.

Snitchler said the immediate challenge is turning that investment into additional electricity supply by accelerating permitting, siting, and grid interconnection. He also cautioned against allowing utilities to finance new generation through mandatory customer charges, arguing that competitive suppliers and investors should continue to bear construction risks.

Claire Lang-Ree, advocate for climate and energy for the Natural Resources Defense Council said, the results confirm that data center growth is outpacing new electricity supply, weakening reliability, and keeping prices at the cap.

She called on PJM and state officials to ensure data centers pay for generation and transmission built to serve them and to accelerate the interconnection of lower-cost clean energy projects.

“The 67 million PJM residents literally can’t afford to suffer any more record-breaking auctions or near-blackout events,” Lang-Ree said.

PJM expects to submit its Reliability Backstop and Connect and Manage proposals to the Federal Energy Regulatory Commission in the coming weeks.

The next Base Residual Auction, for the 2029-2030 delivery year, is scheduled for December as PJM works to restore its three-year-ahead auction cycle.

⚠️ Heat Advisory issued July 27 at 5:48AM CDT until July 27 at 9:00PM CDT by NWS Chicago IL
Today Jul 26
Patchy Fog then Slight Chance Showers And Thunderstorms
90° 70°

Patchy Fog then Slight Chance Showers And Thunderstorms

💨 10 to 15 mph 💧 22%

Leave a Comment





Latest News Stories

frankfort township graphic

Frankfort Township Board Denies Liquor and Gaming Permits for Two Restaurants

Article Summary: The Frankfort Township Board of Trustees denied special use permits for Dimitri Best Food and Kismet Restaurant, both of which were seeking ancillary liquor licenses with the intent to...
summit-hill-junior-high-school-frankfort-161.2

New Hires Approved for Summit Hill District 161

Article Summary: Summit Hill School District 161 approved the hiring of several new staff members, including a District Wide Gifted and Talented Coordinator and multiple paraprofessionals and custodians. The approvals were...
frankfort-park-district

Frankfort Park District Approves $131,500 for Park Upgrades and Master Plan

Article Summary: The Frankfort Park District Board of Commissioners approved agreements totaling $131,500 with planning firm Design Perspectives to design and construct parking lots at two parks and to update master...
frankfort-square-park-district.2

Hunter Prairie Park Redevelopment Moves to Next Phase as Demolition Finishes

Article Summary: The Frankfort Square Park District’s redevelopment of Hunter Prairie Park is progressing, with the demolition phase now complete and work beginning on grading, excavation, and the layout for...
Will County Recorder Graphic.1

Will County Board Approves New Fee Schedule for Recorder of Deeds

Article Summary: The Will County Board has approved a revised fee schedule for the Recorder of Deeds office, which will take effect on October 1, 2025. The changes, based on...
frankfort fire district graphic logo.2

Frankfort Fire District Explores Tax Referendum, Moves to Hire Outreach Consultant

Article Summary: The Frankfort Fire Protection District is taking initial steps toward asking voters for a tax increase for the first time in 25 years, citing revenue challenges and the...
frankfort-school-district-161.2-e1754272831494

Summit Hill 161 Awards $115,905 Contract for Dr. Julian Rogus School Play Area

Article Summary: The Summit Hill District 161 Board of Education unanimously awarded a $115,905 construction contract to Schwartz Construction Group, Inc. for a new play area at Dr. Julian Rogus School....
frankfort fire district graphic logo.2

Frankfort Fire District to Spend $92,000 on New Cardiac Monitors

Article Summary: The Frankfort Fire Protection District Board of Trustees was scheduled to approve the purchase of six new cardiac monitors and related accessories for $91,955 from ZOLL. The acquisition is...
frankfort fire district graphic logo.2

Frankfort Fire District Reviews Tentative Budget for Fiscal Year 2025

Article Summary: The Frankfort Fire Protection District has taken the first step in its annual budgeting process with an initial review of the tentative budget for Fiscal Year 2025. District Accountant...
WCO Board Aug 21.3

Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways

Article Summary: The Will County Board unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on the nation's roadways. The...
Energy advocate applauds oil and gas commingling updates

Energy advocate applauds oil and gas commingling updates

By Tate MillerThe Center Square Oil and gas commingling rules have been updated in accordance with the Big Beautiful Bill in order to strengthen energy production and safety, with energy...
will county board meeting graphic.5

Will County Board Approves Permits for Landscaping Business and Restaurant Liquor Service in Frankfort Area

Article SummaryThe Will County Board unanimously approved three separate special use permits for businesses in the Frankfort area, allowing a landscaping operation in Green Garden Township to continue and two...
will county board meeting graphic.5

Board Approves Engineering Contracts for Mokena Road Widening

Article SummaryThe Will County Board approved over $1.1 million in supplemental engineering contracts to advance the ongoing 80th Avenue improvement project in Mokena. The additional funding addresses project delays and...
will county board meeting.6

Will County Awards $1.46 Million Contract for Kankakee Street Bridge Replacement in Manhattan Township

Article SummaryThe Will County Board has awarded a $1.46 million contract to "D" Construction, Inc. of Coal City to replace the Kankakee Street Bridge over Jackson Creek in Manhattan Township....
will county board meeting.6

Crete Township Community Center to Get New Digital Sign

Article Summary: The Will County Board approved a special use permit and two variances for Crete Township, allowing for the installation of a new on-premise dynamic display sign at its...