Central Ohio data center will have its own power plant
An Ohio state board has approved a natural gas-powered electric generation plant in Licking County to serve a data center, saying taxpayers and ratepayers won’t pay for power at the center.
The power will be consumed by Sidecat, LLC, an affiliate of Meta Platforms, Inc., according to a news release by the Ohio Power Siting Board, which approved the construction of the 250-megawatt natural gas plant.
“Taxpayers and ratepayers will not pay any of the costs,” board spokesman Matthew Butler told The Center Square.
The gas plant, which will be built on 109 acres, will not be physically connected to the electric power grid but will serve only the data center, the release said.
“The project will incorporate 116 MW of battery energy storage to accommodate fluctuations in demand and mitigate unplanned outages,” according to the news release.
The plant will be constructed and operated by Will-Power PH, LLC, the siting board said.
“Will-Power OH must adhere to 36 conditions designed to minimize potential impacts during construction and operation.,” the news release said.
The project will be “within the city of New Albany’s Technology Manufacturing District (TMD) Zone which is a regionally significant corridor for economic growth and development,” according to state documents.
Will-Power will be responsible for the power generation facility design, site development, earthwork, construction, restoration, and operation of the facility.
Will-Power will “own the power generation property, equipment, structures, and on-site Improvements,” according to state documents.
This is the latest in a string of data centers announced for Ohio. The state already has 224 data centers, according to Data Center Maps, which tracks the industry.
Latest News Stories
Ogalla Blasts New State Solar Legislation
Committee Postpones Vote on Brandon Road Fill Operation After Tree Clearing Allegations
Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025
Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena
Meeting Summary and Briefs: Frankfort Public Library District Board of Trustees for October 23, 2025
Misty Creek Development Approved for Sunroom and Patio Additions
Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates
Frankfort Fire Trustees Hold Four-Hour Closed Session on Chief Search
Library Anticipates Purchasing Delays as Major Distributor Closes
P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn
Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee
Village Secures $1.6 Million Grant for Laraway and Pfeiffer Road Multi-Use Path