Frankfort Awards $1 Million Water Main Contract, OKs Well #4 Engineering
Frankfort Village Board Meeting | June 15, 2026
Article Summary: The Frankfort Village Board on Monday, June 15, 2026, awarded a $1,013,407.56 water main replacement contract to Iroquois Paving Corporation and approved a $170,000 engineering agreement for upgrades to its Well #4 treatment plant.
Water System Improvements Key Points:
- Iroquois Paving Corporation won the 2026 Water Main Replacement Program with the lowest of five bids, $1,013,407.56.
- The project replaces aging mains on St. Andrews Way and Glenbarr Lane in the Prestwick Subdivision, addressing dead-end mains and water-quality issues.
- The board separately approved a $170,000 lump-sum engineering agreement with Robinson Engineering for Well #4 Iron Removal Water Treatment Plant upgrades.
- Trustee Maura Rigoni abstained on the Well #4 item, citing her part-time employment with Robinson Engineering.
FRANKFORT — The Frankfort Village Board on Monday, June 15, 2026, advanced two water-system projects on its consent agenda, awarding a roughly $1 million pipe-replacement contract and authorizing engineering work to overhaul an aging treatment plant.
The board adopted a resolution awarding the 2026 Water Main Replacement Program to Iroquois Paving Corporation for $1,013,407.56. The program targets water main improvements on St. Andrews Way and Glenbarr Lane within the Prestwick Subdivision, work the packet says is intended to address both frequent unplanned maintenance and water-quality problems associated with dead-end mains. The village and its consulting engineer, Robinson Engineering, prepared the specifications and opened five bids on May 19, 2026.
Iroquois Paving’s bid came in below the engineer’s $1,380,000 estimate and below all competitors: P.T. Ferro Construction at $1,499,863.90, Steve Spiess Construction at $1,265,605.90, Austin-Tyler Construction at $1,101,323.13 and H. Linden & Sons at $1,216,243.15. Robinson Engineering reviewed the bids and recommended the award to Iroquois Paving as the lowest responsible bidder.
In a separate action, the board adopted a resolution authorizing a $170,000 lump-sum agreement with Robinson Engineering for professional engineering services tied to upgrades at the Well #4 Iron Removal Water Treatment Plant. The facility, located within the Tanglewood Subdivision, was constructed in 2002 as part of a system-wide water-quality effort and now requires significant upgrades due to the age and condition of its equipment, according to the packet.
Before the consent agenda vote, Trustee Maura Rigoni asked that the record reflect her abstention on the Well #4 engineering item, noting that it involves a contract with Robinson Engineering, where she is a part-time employee. Both measures otherwise passed as part of the board’s unanimous consent vote.
Latest News Stories
Beecher Man Charged with 10 Felony Counts for Possession of Child Sex Abuse Material
Frankfort Pushes Back Against State Legislation Threatening Local Zoning Control
Will County Legislative Committee Unanimously Backs Resolution Demanding Return of Local Solar Siting Control
Joseph Perry House Granted Historic Landmark Status
Green Garden Township’s Wildflower Farm Granted Third Extension for Rural Events Permit
Will County Lowers Cedar Road Speed Limit Amid Debate Over Curve Safety and Fatalities
Nine Will County Municipalities Face Expired License Plate Reader Agreements; Crest Hill Opts Out
Judge Orders Will County Board to Approve Previously Denied Solar Farm Permits
WATCH: California probe ends $267M in alleged hospice fraud
Ex-Blago attorney: Quid pro quo is key to Madigan appeal
Illinois Quick Hits: House GOP says no Bears deal without property tax reform
WATCH: More than $600 million stolen from SNAP in 2025