P.T. Ferro

Frankfort Awards $4.46 Million Road Resurfacing Contract to P.T. Ferro

Spread the love

Frankfort Village Board Meeting | June 15, 2026

Article Summary: The Frankfort Village Board on Monday, June 15, 2026, awarded a $4,460,120.95 contract to P.T. Ferro Construction Co. for the 2026 Roadway Maintenance Program, which will resurface 30 street segments totaling 6.81 miles.

2026 Roadway Maintenance Program Key Points:

  • P.T. Ferro Construction Co. submitted the lowest of five bids, at $4,460,120.95.
  • The program covers 30 roadway segments — 6.81 miles — prioritized by pavement age and condition.
  • The village’s fiscal year 2026/2027 budget allocates $5 million in the General Capital Development Fund for the work.
  • The contract carries an October 1 completion date.

FRANKFORT — The Frankfort Village Board on Monday, June 15, 2026, adopted a resolution awarding the village’s largest seasonal infrastructure contract, a $4,460,120.95 agreement with P.T. Ferro Construction Co. for the 2026 Roadway Maintenance Program. The award was approved as part of the board’s unanimous consent agenda.

According to the agenda packet, village staff conducted a comprehensive field survey and evaluated roadway segments based on pavement age and condition to build a prioritized resurfacing list. That review identified 30 street segments totaling 6.81 miles of roadway for this year’s program. The village solicited competitive bids from qualified contractors and opened five proposals on May 20, 2026.

P.T. Ferro Construction Co. came in lowest at $4,460,120.95. The remaining bids were $4,595,721.20 from Gallagher Asphalt Corporation, $4,626,216.36 from D. Construction, Inc., $4,639,910.55 from Austin Tyler Construction and $4,965,026.85 from Iroquois Paving Corporation. Staff noted in the packet that P.T. Ferro has performed similar work for the village previously and “did excellent work,” and recommended accepting the low bid.

The work is funded through the $5 million the village’s fiscal year 2026/2027 budget allocates to the program within the General Capital Development Fund. The packet also itemizes related professional costs, including a design engineering fee of 4 percent of the program amount — about $178,405 — along with $50,000 for pavement coring and an estimated $35,000 for material testing, both handled by subconsultants. Construction is expected to begin as early as possible under a contract completion date of October 1.

At its June 1, 2026, Committee of the Whole meeting, the board reviewed the proposals and forwarded a recommendation to award the contract to P.T. Ferro, the action the full board ratified June 15. A detailed street-by-street list of the segments slated for resurfacing is included in the published agenda packet, available on the village website.

The roadway program is an annual undertaking in Frankfort, with staff rebuilding the priority list each year as pavement ages across the village’s street network.

⚠️ Hydrologic Outlook issued June 20 at 3:30AM CDT by NWS Chicago IL
Today Jun 19
Sunny
78° 59°

Sunny

💨 10 to 15 mph 💧 7%

Leave a Comment





Latest News Stories

Illinois Quick Hits: Nine arrested during Naperville teen gathering

Illinois Quick Hits: Nine arrested during Naperville teen gathering

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Naperville Police say they arrested nine people and issued almost three dozen citations after large groups of...
Rubio provides few answers to Congress on Iran conflict timeline

Rubio provides few answers to Congress on Iran conflict timeline

By Thérèse BoudreauxThe Center Square With the U.S.-Iran conflict approaching the 100-day mark, Secretary of State Marco Rubio defended the Trump administration’s military strategy before a committee of U.S. lawmakers...
Pritzker housing proposal partly stalls amid overreach concerns from localities

Pritzker housing proposal partly stalls amid overreach concerns from localities

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Though the entire affordable housing initiative from Gov. J.B. Pritzker didn’t make it through the General Assembly...
HUD shifts $4B homelessness program from 'Housing First' to treatment

HUD shifts $4B homelessness program from ‘Housing First’ to treatment

By Tim ClouserThe Center Square The U.S. Department of Housing and Urban Development announced a $4 billion funding opportunity for homelessness services on Monday, shifting away from the Housing First...
Poll: Democrats hold slight edge over Rogers in Michigan U.S. Senate race

Poll: Democrats hold slight edge over Rogers in Michigan U.S. Senate race

By Elyse ApelThe Center Square New polling in Michigan's open U.S. Senate race shows each of the leading Democrat candidates narrowly ahead of Republican Mike Rogers in potential general election...
Swipe fee battle continues after delay, court ruling

Swipe fee battle continues after delay, court ruling

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois is still waiting to benefit from a law promised to generate hundreds of millions of dollars...
Walz appoints members to Operation Metro Surge 'Truth Council'

Walz appoints members to Operation Metro Surge ‘Truth Council’

By Elyse ApelThe Center Square Minnesota Gov. Tim Walz has appointed members to a new council tasked with documenting the impacts of Operation Metro Surge and Operation PARRIS, two federal...
$45M included in budget for previously unfunded property tax relief

$45M included in budget for previously unfunded property tax relief

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Included in the recently passed state budget, the Illinois State Board of Education will get money for...
Over one ton of cocaine seized at U.S.-Mexico tunnel bust

Over one ton of cocaine seized at U.S.-Mexico tunnel bust

By Bethany BlankleyThe Center Square Border Patrol agents in Southern California have found another underground cross border tunnel, leading to the arrest of four men and the seizure of enough...
National security group urges Congress to investigate Airwallex ties to CCP

National security group urges Congress to investigate Airwallex ties to CCP

By Tom JoyceThe Center Square A national security group wants Congress to investigate Airwallex over its ties to China. State Armor Chief Executive Officer Michael Lucci sent a letter to...
Open primary system debated as Californians go to polls

Open primary system debated as Californians go to polls

By Chris WoodwardThe Center Square Supporters of California’s top-two open primary system are defending it amid challenges and criticism as voters go to the polls Tuesday in the Golden State's...
Illinois Quick Hits: Pritzker signs two bills

Illinois Quick Hits: Pritzker signs two bills

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker has signed two new laws into effect. House Bill 4154 changes pharmacy licensure provisions...
Elon Poll says 2 in 3 proud to be American and Signers would be disappointed

Elon Poll says 2 in 3 proud to be American and Signers would be disappointed

By Alan WootenThe Center Square Sampling 1,000 adults nationwide ahead of America’s 250th anniversary on July 4, a poll released Tuesday finds 68% are proud to be American and 69%...
U.S. Supreme Court denies Florida request to sue over immigrant CDLs

U.S. Supreme Court denies Florida request to sue over immigrant CDLs

By Michael Carroll | Legal NewslineThe Center Square The U.S. Supreme Court last week swatted away a request from Florida to sue the states of California and Washington over allegations...
Frankfort School District 157-C.2

Meeting Summary and Briefs: Frankfort School District 157-C Board of Education for April 21, 2026

Frankfort School District 157-C Board of Education Meeting | April 21, 2026 The Frankfort School District 157-C Board of Education met April 21, 2026, at the district's administrative office, opening...