Frankfort Awards $4.46 Million Road Resurfacing Contract to P.T. Ferro

Spread the love

Frankfort Village Board Meeting | June 15, 2026

Article Summary: The Frankfort Village Board on Monday, June 15, 2026, awarded a $4,460,120.95 contract to P.T. Ferro Construction Co. for the 2026 Roadway Maintenance Program, which will resurface 30 street segments totaling 6.81 miles.

2026 Roadway Maintenance Program Key Points:

  • P.T. Ferro Construction Co. submitted the lowest of five bids, at $4,460,120.95.
  • The program covers 30 roadway segments — 6.81 miles — prioritized by pavement age and condition.
  • The village’s fiscal year 2026/2027 budget allocates $5 million in the General Capital Development Fund for the work.
  • The contract carries an October 1 completion date.

FRANKFORT — The Frankfort Village Board on Monday, June 15, 2026, adopted a resolution awarding the village’s largest seasonal infrastructure contract, a $4,460,120.95 agreement with P.T. Ferro Construction Co. for the 2026 Roadway Maintenance Program. The award was approved as part of the board’s unanimous consent agenda.

According to the agenda packet, village staff conducted a comprehensive field survey and evaluated roadway segments based on pavement age and condition to build a prioritized resurfacing list. That review identified 30 street segments totaling 6.81 miles of roadway for this year’s program. The village solicited competitive bids from qualified contractors and opened five proposals on May 20, 2026.

P.T. Ferro Construction Co. came in lowest at $4,460,120.95. The remaining bids were $4,595,721.20 from Gallagher Asphalt Corporation, $4,626,216.36 from D. Construction, Inc., $4,639,910.55 from Austin Tyler Construction and $4,965,026.85 from Iroquois Paving Corporation. Staff noted in the packet that P.T. Ferro has performed similar work for the village previously and “did excellent work,” and recommended accepting the low bid.

The work is funded through the $5 million the village’s fiscal year 2026/2027 budget allocates to the program within the General Capital Development Fund. The packet also itemizes related professional costs, including a design engineering fee of 4 percent of the program amount — about $178,405 — along with $50,000 for pavement coring and an estimated $35,000 for material testing, both handled by subconsultants. Construction is expected to begin as early as possible under a contract completion date of October 1.

At its June 1, 2026, Committee of the Whole meeting, the board reviewed the proposals and forwarded a recommendation to award the contract to P.T. Ferro, the action the full board ratified June 15. A detailed street-by-street list of the segments slated for resurfacing is included in the published agenda packet, available on the village website.

The roadway program is an annual undertaking in Frankfort, with staff rebuilding the priority list each year as pavement ages across the village’s street network.

Today Jun 18
Slight Chance Showers And Thunderstorms then Chance Showers And Thunderstorms
59°

Slight Chance Showers And Thunderstorms then Chance Showers And Thunderstorms

Leave a Comment





Latest News Stories

will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
frankfort village hall graphic logo.1

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
frankfort village hall graphic logo.8

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
frankfort illinois library logo graphic.5

Frankfort Library Board Reorganizes with New Officers, Seeks to Fill Vacancy

The Frankfort Public Library District Board of Trustees underwent a significant transformation Thursday night, swearing in five new members, electing a new slate of officers, and announcing an immediate search...
frankfort illinois library logo graphic.1

Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000

The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of...
Meeting-Briefs

Meeting Summary: Frankfort Public Library District for May 22, 2025

The Frankfort Public Library District Board of Trustees held its reorganization meeting on Thursday, welcoming five new members and electing new officers. The board also received an update on the...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...