Frankfort Park District Approves $449,000 in Contracts for Commissioners Park Overhaul

Spread the love

Frankfort Park District Board of Commissioners Meeting | April 14, 2026

Article Summary: The Frankfort Park District Board of Commissioners on Tuesday, April 14, 2026, approved two professional-services contracts totaling $449,000 to advance the state-funded renovation of Commissioners Park, with construction set to begin in May 2026.

Commissioners Park Project Key Points:

  • The board approved a $310,000 agreement with Design Perspectives for design and construction oversight, and a $139,000 agreement with RTM Engineering Consultants for civil, electrical and geotechnical services. Both passed 5-0.
  • The project’s site plan now directs a $350,000 state grant toward expanded parking at Commissioners Park during the renovation, rather than parking lots at Windy Hill and Lincoln Meadows.
  • A representative from Operation Playground presented the board with a $25,000 check toward relocating the dog park out of Commissioners Park.
  • Construction is slated to begin in May 2026, with the design package expected to go before the Village of Frankfort within 30 days.

FRANKFORT — The Frankfort Park District Board of Commissioners on Tuesday, April 14, 2026, approved two professional-services agreements worth a combined $449,000 to move forward with the long-planned renovation of Commissioners Park, a project supported by state grant funding through the Illinois Department of Commerce and Economic Opportunity (DCEO).

Meeting in a special session at the Founders Community Center, 140 Oak Street, the board voted 5-0 to approve a $310,000 agreement with Design Perspectives for design and construction oversight, and a separate $139,000 agreement with RTM Engineering Consultants for civil and electrical engineering and geotechnical services tied to the renovation. Both motions were made by Treasurer Mark Ponton and seconded by Secretary Tom Ruvoli.

Executive Director Gina Hassett told the board the project’s site plan has been solidified. Under the revised plan, the district will direct its $350,000 in grant funding toward additional parking at Commissioners Park during the renovation, a change from an earlier concept that would have applied the money to parking improvements at Windy Hill and Lincoln Meadows. Hassett said state Sen. Michael Hastings indicated he would try to secure additional funding in the future for the Windy Hill and Lincoln Meadows lots. Staff have shared the design with Hastings and with local youth athletic groups.

Funding and Design Details

Hassett said that to move the project forward and finalize grant paperwork, the district needed to engage a firm for construction documents, permitting, bid package development, construction observation and engineering services. She recommended continuing with Design Perspectives, which has already been working on the project, and said she had worked with the firm to bring its cost within budget. She added that contingencies are available for additional features.

Frankfort Baseball has asked whether the second phase of the t-ball fields could be bid as an alternate, as the group would like to fund that portion of the work itself, Hassett said. She described the finished result as a fully completed park with ADA-accessible walkways and provided a timeline showing work beginning in May 2026. Staff will try not to disrupt the athletic groups during construction, and the design is expected to be ready to take to the Village of Frankfort within the next 30 days.

Historian Tom Barz raised questions during the discussion. He said more shade is needed near the ball fields and suggested incorporating an area where an ice-skating rink could be set up. Barz also voiced concern about some of the project fees, worrying that certain estimates were set on the high end and that if actual costs came in lower, the district would be locked into paying the approved amount. Superintendent of Building and Grounds Edward Newton and Superintendent of Recreation Stacy Proper both said they were looking forward to the improvements.

Dog Park Relocation Funding

The renovation is tied to the planned relocation of the dog park out of Commissioners Park. During citizens’ comments, Operation Playground representatives Chris Herder and Dave McDonald presented the board with a $25,000 check toward that relocation. The group raised the money through its Pours for Parks event and Frankfort Fest parking, and Hassett said the amount is in addition to previous Operation Playground donations being held for the project.

President Michael McCarey said he attended a recent meeting with residents living near the proposed dog park relocation site, where one resident concern was water retention in the park.

The Commissioners Park renovation has drawn community interest. Regan Frietag Pattison of Harber Contractors, who lives in Homer Glen and works with Frankfort Township on its food pantry, told the board she and her children use Frankfort parks and that she is very interested in the Commissioners Park project.

Leave a Comment





Latest News Stories

Meeting-Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
frankfort illinois library logo graphic.1

Frankfort Library Secures $83K Grant for Reading Room, Financial Report Shows Strong Position

FRANKFORT, IL – The Frankfort Public Library is poised to begin its next major renovation after the State Library confirmed it has qualified for a matching grant of up to...
frankfort illinois library logo graphic.5

Frankfort Library Considers Limiting Digital Access on Educator Cards to Manage Costs

FRANKFORT, IL – The Frankfort Public Library is exploring a change to its digital lending policies for local educators to manage the rising costs and high demand for popular streaming...
frankfort illinois library logo graphic.1

Newly Appointed Trustee Brooks Stenoish Takes Oath, Finalizing Frankfort Library Board

FRANKFORT, IL – The Frankfort Public Library District Board of Trustees is now at its full seven-member strength after newly appointed trustee Brooks Stenoish was officially sworn in at Thursday...
Meeting-Briefs

Meeting Summary: Frankfort Public Library District for June 26, 2025

The Frankfort Public Library District Board of Trustees held its regular monthly meeting on Thursday. The board swore in its newest member, reviewed a strong year-end financial report, and approved...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Screenshot-2025-07-06-at-9.50.39-AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot-2025-07-06-at-9.45.35-AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...