Will County Planning and Zoning Commission Recommends Denial of 6,099-Acre Earthrise Solar Project After Court-Ordered Hearing

Spread the love

Will County Board Special Planning and Zoning Commission Meeting | May 12, 2026

Article Summary: Following a court-mandated cross-examination hearing, the Will County Planning and Zoning Commission voted 1-4 to recommend denial of a special use permit for the massive Lincoln Solar Energy project spanning three townships.

Earthrise Solar Project Key Points:

  • The PZC voted 1-4 against the special use permit for the 600 MW solar facility (Ordinance #26-109 / Case ZC-25-129) proposed by Earthrise Energy.

  • The special meeting was mandated by a court order (26CH79) from Judge Breslin to allow plaintiffs to cross-examine developers due to alleged due process violations.

  • Plaintiffs argued the application was incomplete, citing missing field data for “farmed wetlands” and public safety risks.

  • The $1.2 billion project footprint encompasses roughly 6,099 acres across Manhattan, Green Garden, and Wilton townships.

The Will County Board Planning and Zoning Commission on Tuesday, May 12, 2026, voted 1-4 to recommend denial of a special use permit for a sprawling 6,099-acre commercial solar facility, following a contentious, court-ordered cross-examination hearing.

Earthrise Energy, operating under Lincoln Solar Energy, LLC, applied for a special use permit to build a 600-megawatt solar facility across 96 parcels in Manhattan, Green Garden, and Wilton townships. The facility would connect to the grid via the existing Lincoln natural gas peaking plant. While the PZC had previously voted to recommend denial in March, Tuesday’s special meeting was mandated by a temporary restraining order from Judge Breslin. The court order allowed plaintiffs to cross-examine the developers, a process the plaintiffs’ attorney claimed the county had illegally bypassed for years.

“The reason you haven’t heard this before is for some reason in this county there’s not been any cross-examination for years during a special use application,” Plaintiff Attorney Steven Becker told the commission. “That’s what we won in front of Judge Breslin… this is a new procedure that was apparently being bypassed by Will County unbeknownst to me.”

During the cross-examination, Becker grilled Earthrise Lead Developer Robert Kalbouss over the company’s environmental reviews, specifically focusing on the delineation of wetlands and the potential for heavy metal leaching into the groundwater. Becker argued that the application was incomplete because Earthrise relied primarily on a National Wetland Inventory (NWI) data set from the U.S. Fish and Wildlife Service rather than waiting for fields to lie fallow to properly field-delineate “farmed wetlands.”

“If a field is being tilled, you cannot determine hydrophytic vegetation. You have to wait until it is fallow,” Becker argued. “This application is woefully incomplete.”

Earthrise attorney Ben Jacobi fiercely defended the application, noting that the company updated its site plan on March 5, 2026, and submitted a supplemental memorandum on May 8 detailing complete field delineations. Jacobi stated that the project was designed to completely avoid all permanent impacts to wetlands.

“They’re going to avoid them all. They’re going to assume the jurisdiction of the wetland, and they’re going to avoid them all,” Jacobi said. “And so, that’s really important that that eliminates the wetland as an issue entirely.”

The developer also faced questions about why outreach meetings were not held in Green Garden or Wilton townships. Kalbouss confirmed that public information meetings were only hosted in Manhattan Township, citing “the hostility that we observed online from the township” as the reason for not holding open forums in the other jurisdictions.

Prior to the final vote on the special use permit, the PZC voted unanimously to amend conditions 3, 5, and 6 of the permit to match language recently approved by the Will County Board for the Plum Valley Solar project.

However, when the amended special use permit was called to a vote, it failed in a 1-4 split. Commissioner Lewis Navarat voted yes, while Vice Chairman John Kiefner, Commissioner Matt Garland, Commissioner Karen Warrick, and Chairman Hugh Stipan voted no.

The 192 variances associated with the project—allowing for 36-inch ground cover plant heights and a reduction in mandatory mowings—were previously approved during a March 31 meeting and were not subject to Tuesday’s vote. The PZC’s denial recommendation will now move forward to the Will County Board for final consideration.

⚠️ Air Quality Alert issued July 13 at 11:44AM CDT by NWS Chicago IL
Mon Jul 13
Sunny
94° 73°

Sunny

💨 0 to 5 mph 💧 0%

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for July 15, 2025

The Frankfort Fire Protection District Board of Trustees took major steps toward addressing long-term financial and operational needs at its meeting on July 15, 2025. The board directed its interim...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Square Park District for July 17, 2025

The Frankfort Square Park District Board of Commissioners on Thursday, July 17, 2025, heard positive updates on major capital projects and celebrated the national success of its BDC dance program....
frankfort fire district graphic logo.4

Frankfort Fire District Faces Tighter Budget, Rising Overtime in FY 2025 Outlook

Article Summary: A preliminary review of the Frankfort Fire Protection District's fiscal year 2025 budget indicates a smaller surplus than the previous year, driven by rising overtime costs and an...
fall-festival-b2adf834-992f-4ebd-ac09-edfc1d11b40a-circle

Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event

FRANKFORT, IL – The heart of historic downtown Frankfort is set to transform into a vibrant hub of art, music, and community spirit for the 57th annual Frankfort Fall Festival. Running...
frankfort illinois library logo graphic.1

Frankfort Library Tables Reading Room Project Over Higher-Than-Expected Engineering Costs

Article Summary: The Frankfort Public Library Board of Trustees voted to table a proposal from architectural firm StudioGC for a planned reading room project after engineering fees came in significantly...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Township Board for July 14, 2025

The Frankfort Township Board on Monday, July 14, 2025, primarily focused on zoning matters, unanimously denying special use permits for two businesses, Dimitri Best Food and Kismet Restaurant, that sought...
frankfort-park-district

Frankfort Park District Board Approves Pay Raise for Executive Director Gina Hassett

Article Summary: Following a closed session, the Frankfort Park District Board of Commissioners unanimously approved a compensation increase for Executive Director Gina Hassett. The decision was made during the board's regular...
Meeting Briefs

Meeting Summary and Briefs: Summit Hill School District 161 for July 9, 2025

The Summit Hill School District 161 Board of Education took several key actions at its meeting on Wednesday, July 9, 2025, highlighted by the unanimous approval of a $115,905 contract...
frankfort-square-park-district.2

Park District’s BDC Dance Program Earns National Recognition

Article Summary: The Frankfort Square Park District’s Board of Commissioners celebrated the national success of its BDC dance program, which recently won numerous accolades, including a studio excellence award, at...
frankfort fire district graphic logo.3

Frankfort Fire District and Firefighters Union to Discuss Possible Referendum

Article Summary: The Frankfort Fire Protection District Board of Trustees has called a special meeting for July 25 to discuss a "possible referendum" with representatives from the Associated Fire Fighters of...
WCO Board Aug 21.4

After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business

Article Summary: In a rare reversal, the Will County Board approved a special use permit for a landscaping business in a residential area of DuPage Township after the measure initially...
frankfort fire district graphic logo.3

Frankfort Fire Board Approves $460,000 Purchase of New Cardiac Monitors

Article Summary: The Frankfort Fire Protection District Board of Trustees unanimously approved a five-year, $459,775 agreement to acquire six new, state-of-the-art cardiac monitors. The purchase replaces aging equipment that is...
Frankfort-Township-Logo-Graphic

Frankfort Township Highway Department Upgrades Aging Fleet, Starts Grant Project

Article Summary: The Frankfort Township Highway Department is in the process of replacing equipment that is up to two decades old, having recently received a new small leaf vacuum and a...
summit-hill-junior-high-school-frankfort-161

Summit Hill 161 Board Split on Administrative Assignments, Contracts

Article Summary: The Summit Hill District 161 Board of Education showed rare division in two separate 6-1 votes to approve administrative assignments and contracts for the upcoming school year. Board member...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for August 21, 2025

The Will County Board received County Executive Jennifer Bertino-Tarrant’s proposed $791 million budget for fiscal year 2026, which holds the line on the property tax levy while funding key services....