Millions Approved for Will County Highway and Road Infrastructure Projects
Will County Board Meeting | April 16, 2026
Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road, and Laraway Road.
Infrastructure Key Points:
-
Austin Tyler Construction was awarded a $2,984,218.25 contract to rebuild and widen Francis Road.
-
P.T. Ferro Construction secured a $958,266.60 contract to resurface Renwick Road.
The Will County Board on Thursday, April 16, 2026, greenlit a slate of major infrastructure investments across the region, passing multiple resolutions on the consent agenda without opposition.
The largest expenditure was authorized by Resolution 26-113, which awarded a $2,984,218.25 contract to Austin Tyler Construction, Inc. The Elwood-based firm was the low bidder for a comprehensive project on Francis Road (County Highway 64) from Gougar Road to Wirt Road in County Board District 5. The scope of work includes roadway reconstruction and widening, storm sewer installation, drainage ditch improvements, culvert reconstruction, and retaining wall installation. The project is slated to begin in June 2026, during which the road will be closed to through traffic.
In Plainfield Township, the Board approved Resolution 26-114, confirming a $958,266.60 contract with Joliet-based P.T. Ferro Construction Co. The firm will resurface Renwick Road (CH 36) from east of U.S. Route 30 to west of Weber Road. The project, which also begins in June, will utilize Hot-Mix Asphalt (HMA) surface removal and replacement, centerline rumble strips, and deck slab repairs. The roadway will remain open during construction with periodic lane closures guided by flaggers. P.T. Ferro also secured a separate $194,014.90 contract (RES 26-115) to resurface various subdivision roadways within the Plainfield Road District.
The Board also took action on Laraway Road in New Lenox. Resolution 26-112 authorizes an agreement with LNS Development Group, LLC for stormwater management improvements along Laraway Road between Cedar Road and Spencer Road. The county will reimburse the developer an estimated $352,071.95 for the construction of a shared detention facility and storm sewer upgrades required for the county’s future plans to widen Laraway to a four-lane, barrier-median roadway.
Latest News Stories
WATCH: Republican leader: says Pritzker budget cut EO a ploy for IL tax increases
Judge’s questions during IL gun ban arguments gives rights advocates ‘hope’
Illinois agencies to post monthly investment reports, lawmaker calls symbolic
JJC Board Approves Contract with Adjunct Faculty Union
JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate
Meeting Summary and Briefs: Summit Hill School District 161 for August 13, 2025
Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute
Summit Hill 161 Accepts a Dozen Resignations, Approves New Hires
Summit Hill 161 Approves $48K Tech Upgrade, Board Divided on New Teacher Hire
Meeting Summary and Briefs: Frankfort Village Board for September 8, 2025
Frankfort Resident Questions Village’s Lake Michigan Water Survey Process
Meeting Summary and Briefs: Frankfort Public Library District for July 24, 2025