Article Summary: The Will County Facilities Department announced the successful completion of the Veterans Assistance Commission (VAC) building renovations and the installation of a new full-body scanner at the River Valley Justice Center.

Facilities Update Key Points:

  • The VAC buildout at 1300 Copperfield is officially complete, and staff have moved in.

  • A new full-body scanner was successfully installed in the visitation area of the River Valley Justice Center.

  • The Facilities Department completed over 550 work orders in March, averaging $15 per order with a 98% on-time completion rate.

  • Will County met its 100% Demand Response energy reduction goal for peak shaving.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, received an extensive operations update from the Facilities Department, highlighting the completion of a major renovation and significant security upgrades.

Director of Facilities William Fern and Ken Rogalski presented the April 2026 Facilities Update, announcing that the Veterans Assistance Commission (VAC) buildout at 1300 Copperfield is fully complete. The project included a total roof replacement, glass replacement, and interior space renovations. The ribbon-cutting ceremony was held recently, and staff have officially moved into the owned facility, successfully eliminating another county lease.

Security and safety upgrades were also a major focus for the month. Rogalski reported the successful installation of a new full-body scanner in the visitation area of the River Valley Justice Center (3200 W McDonough St).

“It was like a two-day project. It turned out really good,” Rogalski noted.

Additionally, Life Safety Specialist Aaron Kozlowski has been touring county buildings to update emergency evacuation plans and conduct CPR and AED training. The county’s Finance Department recently completed the life-saving training, and “Stop the Bleed” classes are scheduled to begin soon.

In general maintenance news, the Facilities Department completed over 550 work orders in March, representing over 300 hours of labor. The department maintained a highly efficient average cost of $15.00 per work order and achieved a 98% on-time completion rate. Rogalski also highlighted that the county successfully hit its 100% Demand Response energy reduction goal for summer peak shaving electrical curtailment.

The committee also took a moment to honor Facilities Team member Dan Shields, who recently celebrated his 35th anniversary working for Will County.

⚠️ Hydrologic Outlook issued June 16 at 2:13PM CDT by NWS Chicago IL
⚠️ Hydrologic Outlook issued June 16 at 2:12PM CDT by NWS Chicago IL
Tue Jun 16
Showers And Thunderstorms
71° 59°

Showers And Thunderstorms

💨 5 to 20 mph 💧 99%

Leave a Comment





Latest News Stories

Will County Finance Logo

Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026

Will County Finance Committee Meeting | March 3, 2026 The Will County Board Finance Committee met on Tuesday to review a slate of year-end financial reports and approve routine budget...
frankfort village hall graphic logo.1

Frankfort Board Awards $551,755 in Engineering Contracts for Aberdeen Bridge Replacement

Frankfort Village Board Meeting | March 16, 2026 Article Summary: Following emergency shoring improvements, the Village Board approved structural and design engineering contracts to fully replace the Aberdeen Bridge over...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for March 10, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, March 10, 2026, to review a backlog...
frankfort village hall graphic logo.8

Frankfort Village Board Approves Preliminary Plans for 133-Acre Frankfort Pointe Development Amid Resident Concerns

Frankfort Village Board Meeting | March 16, 2026 Article Summary: The Village Board approved rezoning and preliminary plans for a massive mixed-use industrial, commercial, and solar development on the village’s...
Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...