Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

Today Jun 11
Sunny
80° 61°

Sunny

💨 10 to 15 mph 💧 0%

Leave a Comment





Latest News Stories

U.S. sees progress in Iran talks, Tehran says no deal yet

U.S. sees progress in Iran talks, Tehran says no deal yet

By Elyse ApelThe Center Square A top Iranian official says a deal to end the conflict between the U.S. and Iran is not imminent, despite earlier suggestions from U.S. officials...
frankfort fire district graphic logo.2

Frankfort Fire District Approves $260,517.79 in Bills, Reappoints Fire Commissioner Dauber

Frankfort Fire Protection District Board of Trustees Meeting | April 21, 2026 Article Summary: The Frankfort Fire Protection District Board of Trustees approved $260,517.79 in Fire Service and Ambulance Fund...
frankfort-park-district

Frankfort Park District Updates Vehicle Policy on Take-Home Use

Frankfort Park District Board of Commissioners Meeting | April 14, 2026 Article Summary: The Frankfort Park District Board on Tuesday, April 14, 2026, unanimously approved an addition to its vehicle...
Screenshot 2026-05-21 at 5.01.25 PM

Frankfort Approves $1.1 Million in Fleet Upgrades and Sewer Infrastructure Contracts

Frankfort Village Board Meeting | May 18, 2026 Article Summary:The Frankfort Village Board authorized more than $900,000 in public works fleet replacements, including a new Vactor truck and dump truck,...
Everyday Economics: History doesn't repeat, but the Fed Is hearing an echo

Everyday Economics: History doesn’t repeat, but the Fed Is hearing an echo

By Orphe DivounguyThe Center Square Read this week's Fed minutes carefully and you'll hear 1970s.The Fed has stopped debating when to cut. Now it's debating whether to hold higher for...
Illinois DHS appointment sparks backlash over alleged voter registration mailer practices

Illinois DHS appointment sparks backlash over alleged voter registration mailer practices

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The appointment of Illinois Department of Human Services Secretary Dulce Quintero is drawing renewed criticism from...
Arctic defense begins in Galveston after Memorial Day

Arctic defense begins in Galveston after Memorial Day

By Bethany BlankleyThe Center Square As Texans celebrate Memorial Day weekend, 190 years of Texas independence and 250 years of American independence this year, they are also celebrating a new...
Illinois Quick Hits: Pritzker urges megaprojects support for Bears

Illinois Quick Hits: Pritzker urges megaprojects support for Bears

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker says megaprojects legislation is shaping up in the Illinois Senate. A reporter asked the...
Frankfort School District 157-C.1

Frankfort School District 157-C Approves New Honors Criteria, Hires Student Services Director at April Meeting

Frankfort School District 157-C Board of Education Meeting | April 21, 2026 Article Summary: The Frankfort School District 157-C Board of Education on April 21, 2026, approved the hiring of...
Screenshot 2026-05-23 at 7.23.02 PM

Lincoln-Way 210 Backs Mokena Downtown TIF Extension to 2044

Lincoln-Way Community High School District 210 Meeting | May 21, 2026 Article Summary: The Lincoln-Way Community High School District 210 Board of Education on Thursday, May 21, 2026, voted unanimously...
frankfort township graphic

Frankfort Township Board Granted Authority to Sell Lighthouse Pointe Senior Housing Lots

Frankfort Township Annual Town Meeting | April 14, 2026 Article Summary: The Frankfort Township electorate, meeting at the April 14, 2026, Annual Town Meeting, voted to delegate to the Township...
Shooting outside White House leaves one dead, one injured

Shooting outside White House leaves one dead, one injured

By Sarah Roderick-FitchThe Center Square Two people were shot, including the suspected gunman, in a shooting outside the White House Saturday night. The suspected gunman was shot and killed by...
frankfort-park-district

Frankfort Park District Approves $449,000 in Contracts for Commissioners Park Overhaul

Frankfort Park District Board of Commissioners Meeting | April 14, 2026 Article Summary: The Frankfort Park District Board of Commissioners on Tuesday, April 14, 2026, approved two professional-services contracts totaling...
Bill to let felons vote from prison draws criticism from Republicans

Bill to let felons vote from prison draws criticism from Republicans

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Some Democrats and electoral rights groups want progress on legislation in Springfield that would give people in...
Supreme Court yet to decide high profile cases

Supreme Court yet to decide high profile cases

By Andrew RiceThe Center Square Birthright citizenship, transgender athletes in female sports and federal firing powers are among more than two dozen cases yet to be decided by the U.S....