WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Spread the love

Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

Today Jun 11
Sunny
80° 61°

Sunny

đź’¨ 10 to 15 mph đź’§ 0%

Leave a Comment





Latest News Stories

Screenshot 2025-10-17 at 1.51.22 PM

Deniz Aslan Appointed Interim Director of Curriculum at Summit Hill 161

Summit Hill School District 161 Board Meeting | September 17, 2025 Article Summary: The Summit Hill District 161 Board of Education appointed longtime educator Deniz Aslan as the Interim Director...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Public Library District for August 28, 2025

The Frankfort Public Library District Board of Trustees approved its budget for the upcoming fiscal year, advanced a long-awaited reading room renovation, and authorized spending on key facility maintenance projects...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for August 19, 2025

The Frankfort Fire Protection District Board of Trustees made a firm financial commitment to its pursuit of a future tax referendum at its meeting on Tuesday, August 19, 2025. The...
frankfort illinois library logo graphic.1

Frankfort Library Approves Funds for New Heaters, Tree Removal

Article Summary: The Frankfort Public Library Board of Trustees approved nearly $20,000 in spending for essential building and grounds maintenance, including the replacement of several heating units and the removal...
Screenshot 2025-10-17 at 1.51.14 PM

Summit Hill 161 Welcomes Will County Sheriff’s Deputy as New School Resource Officer

Summit Hill School District 161 Board Meeting | September 17, 2025 Article Summary: Summit Hill School District 161 officially introduced Will County Sheriff's Deputy Justin Farkas as the district's new...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Square Park District for August 21, 2025

The Frankfort Square Park District Board of Commissioners reviewed a clean annual audit, heard a detailed presentation from the Lincolnway Special Recreation Association (LWSRA), and approved several administrative measures at...
frankfort fire district graphic logo.6

Frankfort Fire Board Adopts FY 2026 Budget Amid Rising Insurance Costs

Article Summary: The Frankfort Fire Protection District Board of Trustees has unanimously adopted its budget and appropriation ordinance for the 2026 fiscal year. The approval came after a public hearing...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
About Us Website Header - 1

Library Approves $14,700 for Reading Room Architectural Services

Article Summary: The Frankfort Public Library board has approved a $14,700 proposal from StudioGC for architectural services for its long-planned reading room project, moving the renovation forward after it was...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Township Board for August 11, 2025

The Frankfort Township Board of Trustees on Monday, August 11, 2025, passed a significant resolution empowering Supervisor Nick George to negotiate the development of township-owned real estate, a move aimed...
Screenshot 2025-10-17 at 1.50.57 PM

Summit Hill 161 Board Approves $40 Million Budget for 2025-2026 School Year

Summit Hill School District 161 Board Meeting | September 17, 2025 Article Summary: The Summit Hill School District 161 Board of Education unanimously approved a roughly $40 million budget for...
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
frankfort-square-park-district.2

LWSRA Details Services for Residents with Disabilities, Plans ‘Hero Village’ Grand Opening

Article Summary: Keith Wallace, Executive Director of the Lincolnway Special Recreation Association (LWSRA), presented an overview of the agency’s services to the Frankfort Square Park District board, highlighting its support...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Park District for August 12, 2025

The Frankfort Park District Board of Commissioners on Tuesday, August 12, 2025, approved a significant construction change order for the Fort Frankfort project and received updates on the use of...
frankfort fire district graphic logo.2

Frankfort Fire District Hires Two Firms for Over $70,000 to Lead Referendum Campaign

Article Summary: The Frankfort Fire Protection District has officially committed to a community outreach campaign for a potential tax referendum, approving agreements with both a professional consulting firm and the...