Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

⚠️ Hydrologic Outlook issued June 16 at 2:44AM CDT by NWS Chicago IL
Today Jun 15
Showers And Thunderstorms Likely then Chance Showers And Thunderstorms
72° 55°

Showers And Thunderstorms Likely then Chance Showers And Thunderstorms

💨 10 to 20 mph 💧 71%

Leave a Comment





Latest News Stories

Screenshot 2025-12-20 at 12.15.00 PM

The Lakota Group Tapped for Historic Downtown Frankfort Design Study

Frankfort Village Board Meeting | December 15, 2025 Article Summary: The Frankfort Village Board on Monday, Dec. 15, 2025, authorized a professional services agreement with The Lakota Group to conduct...
Will County Board Graphic.02

Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Will County Community Mental Health Board provided a quarterly update, outlining the timeline and strategic priorities for...
summit-hill-junior-high-school-frankfort-161.2

Clean Audit Reveals $8.5 Million Increase in District 161 Net Position

Summit Hill School District 161 Meeting | December 17, 2025 Article Summary: An independent audit of Summit Hill School District 161’s 2024-2025 fiscal year has returned a "clean" opinion, showing...
Will County P&Z Logo Planning Zoning

PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a new landscape business on...

JJC Foundation Executive Director Retires Following $2.3 Million Estate Gift

Joliet Junior College Board Meeting | Dec. 10, 2025 Article Summary: Longtime Joliet Junior College Foundation Executive Director Kristi Mulvey announced her retirement at her final board meeting, capping a...
Screenshot 2025-12-20 at 12.25.51 PM

Lincoln-Way Board Approves $92.5 Million Tax Levy for 2025

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The Lincoln-Way Community High School District 210 Board of Education officially adopted a $92,522,000 tax levy during...
frankfort-school-district-161.2-e1754272831494

Summit Hill District 161 Board Approves $44.8 Million Tax Levy with Slight Overall Decrease

Summit Hill School District 161 Meeting | December 17, 2025 Article Summary: The Summit Hill School District 161 Board of Education on Tuesday approved a 2025 tax levy that represents...
Screenshot 2025-12-20 at 12.14.44 PM

Frankfort Board Approves 2025 Tax Levy with Projected Rate Decrease

Frankfort Village Board Meeting | December 15, 2025 Article Summary: The Frankfort Village Board on Monday, Dec. 15, 2025, approved a $4,069,066 tax levy for the 2025 fiscal year. Despite...
frankfort fire district graphic logo.2

Interim Chief Interviews for Permanent Job as Frankfort Fire Board Meets in Closed Session

Frankfort Fire Protection District Meeting | December 8, 2025 Article Summary: Interim Fire Chief Paul Kinsella formally interviewed for the permanent leadership position at the Frankfort Fire Protection District on...
Will County Board Graphic.04

Liquor License Amendments Approved for Frankfort, Joliet, and Lockport Businesses

Will County Board Executive Committee Meeting | December 11, 2025 Article Summary: The Executive Committee approved amendments to the County’s Liquor Control Ordinance to increase the number of available licenses,...
frankfort fire district graphic logo.2

Frankfort Fire Trustees Hire Illinois Fire Chiefs Association to Assist in Chief Search; One Trustee Dissents

Frankfort Fire Protection District Meeting | November 18, 2025 Article Summary: The Frankfort Fire Protection District Board of Trustees has voted to engage the Illinois Fire Chiefs Association to assist...
Planning & Zoning Graphic.3

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 16, 2025

Will County Planning and Zoning Commission Meeting | December 16, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission navigated attendance issues during its December 16, 2025, meeting, beginning...
Will County P&Z Logo Planning Zoning.2

Joliet Property Owner Cleared to Convert Non-Conforming Building into Two-Unit Residence

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: The Planning and Zoning Commission legalized the status of a Joliet residence that had previously contained four illegal...
Meeting-Briefs

Meeting Summary and Briefs: Frankfort Square Park District for Nov. 20, 2025

Frankfort Square Park District Meeting | Nov. 20, 2025 The Frankfort Square Park District Board of Commissioners met on Wednesday, November 20, 2025, at the Square Links Golf Course Clubhouse....
Meeting Briefs

Meeting Summary and Briefs: Will County Committee of the Whole for Dec. 2025

Will County Committee of the Whole Meeting | December 2025 Overall Meeting SummaryThe Will County Board Committee of the Whole met on Tuesday, Dec. 9, 2025, for a series of...