Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | March 19, 2026

Article Summary: The Board of Education approved a $1.98 million contract with CDW/Greatline Solutions to upgrade aging wired infrastructure at the Central and East campuses to support modern technology and faster network speeds.

Cabling Upgrade Key Points:

  • A contract for a total cost of $1,982,901.00 was awarded to CDW/Greatline Solutions.

  • The project replaces 20-to-25-year-old CAT 5e cabling with CAT 6A, supporting up to 10 gigabits per second.

  • The district anticipates receiving $480,000 in reimbursements through the federal E-Rate program.

  • The new cabling comes with a 25-year manufacturer warranty.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, March 19, 2026, unanimously approved a contract for a total cost of $1,982,901.00 with CDW/Greatline Solutions for a district-wide wired infrastructure upgrade.

The district issued a Request for Proposals (RFP) in January 2026 to upgrade components of its wired infrastructure through the federal E-Rate process. According to Director of Technology Cheryl Kay, much of the existing cabling at Lincoln-Way Central and East is 20 to 25 years old. The older CAT 5 and CAT 5e cabling standards do not support the faster speed capabilities of modern switching and wireless equipment recently purchased by the district.

“To put this into perspective for you, CAT 5e cabling supports speeds up to 1 gigabit per second, while CAT 6A cabling can support speeds up to 10 gigabits per second,” Kay explained to the Board. “I’ve used the garden hose versus the fire hose analogy in the past. So essentially, the new cabling allows more data to move through the network at one time.”

The upgraded infrastructure will also establish a foundation for future technology projects, including IP communication systems, digital signage, emergency alerting, and intercom systems that are nearing the end of their usable life.

The district received three proposals. While Netsource Solutions submitted a lower bid of $1,885,001.00, the district rejected it because the company only had 25 total employees. Kay noted that the district had significant concerns about a company of that size being able to complete the massive scope of work on time across multiple buildings. CDW/Greatline, a vendor the district has successfully used for past fiber projects, was selected instead.

The project is included in the district’s 5-year technology plan. Because a significant portion of the work qualifies for E-Rate reimbursements, the district anticipates receiving roughly $480,000 back after the project is completed. The installation work will be completed between April 1, 2026, and September 30, 2027, working around the district’s upcoming HVAC construction schedule.

Leave a Comment





Latest News Stories

frankfort-park-district

Frankfort Park District Approves Over $322,000 in August Bills

Frankfort Park District Meeting | September, 2025 Article Summary: The Frankfort Park District Board of Commissioners approved the payment of bills totaling $322,856.04 for August, which included a delayed payment for...
Screenshot 2025-10-25 at 10.14.46 AM

Frankfort Board Approves New Dump Truck Purchase, Sale of Surplus Vehicles

Village of Frankfort Board Meeting | October 20, 2025 Article Summary: The Frankfort Village Board authorized the purchase of a new 2026 Ford F-450 dump truck for an amount not...
Screenshot 2025-10-25 at 10.14.28 AM

Frankfort Approves Over $203,000 for Holiday Lighting Contract

Village of Frankfort Board Meeting | October 20, 2025 Article Summary: The Frankfort Village Board awarded a three-year contract for holiday lighting and decorations totaling $203,269 to Wingren Landscape, Inc....
Meeting Briefs

Meeting Summary and Briefs: Summit Hill School District 161 for October 15, 2025

Summit Hill School District 161 | October 15, 2025 The Summit Hill School District 161 Board of Education on Wednesday, October 15, 2025, reviewed highly positive preliminary data from the...
Screenshot 2025-10-25 at 12.42.59 PM

Will County Committee Grapples with $8.9 Million Budget Gap After Contentious 0% Tax Levy Vote

Will County Board Finance Committee Meeting | October 21, 2025 Article Summary: The Will County Board Finance Committee held a contentious debate over how to close an $8.9 million budget shortfall...
Screenshot 2025-10-25 at 10.14.13 AM

Frankfort Earns Clean Audit, Receives National Finance Award for 35th Consecutive Year

Village of Frankfort Board Meeting | October 20, 2025 Article Summary: The Village of Frankfort has received an unmodified "clean" opinion on its annual audit for the fiscal year ending...
Poll: Young adults not confident in 2026 election fairness

Poll: Young adults not confident in 2026 election fairness

By Andrew RiceThe Center Square Almost half of young adult voters are not confident the 2026 elections will be conducted fairly, according to a new poll. The Center Square’s Voters’...
Narco interdiction at sea isn’t new, CBP, Coast Guard have been doing it for years

Narco interdiction at sea isn’t new, CBP, Coast Guard have been doing it for years

By Bethany BlankleyThe Center Square President Donald Trump is ordering an aircraft carrier strike group head to the Caribbean to assist with drug interdiction at sea. This is after he...
Government shutdown halts visa, permanent resident approvals

Government shutdown halts visa, permanent resident approvals

By Andrew RiceThe Center Square As the federal government shutdown continues with no clear end in sight, federal agencies that process legal immigrant petition documents have been completely halted, leaving...
Frankfort Village Board Meeting Graphic

Frankfort Approves Plan for 43-Home First Phase of Stalled Country Crossing Subdivision

Village of Frankfort Board Meeting | October 20, 2025 Article Summary: The Frankfort Village Board has approved amended annexation agreements and a final plat for the first phase of the...
Ads roll on, money pours in, and SCORE Act waits

Ads roll on, money pours in, and SCORE Act waits

By Alan WootenThe Center Square Seven big games in the Southeastern Conference alone, hundreds of players, all headed toward the billions college football generates in the 21st century. And with...
Primary election filing to begin Monday for Illinois Dem, GOP candidates

Primary election filing to begin Monday for Illinois Dem, GOP candidates

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Candidates hoping for a spot on 2026 primary election ballots are expected to line up Monday outside...
summit-hill-junior-high-school-frankfort-161.2

Student Initiative Leads to Lunch Program Overhaul at Summit Hill

Summit Hill School District 161 | October 15, 2025 Article Summary: A student-led effort at Summit Hill Junior High is sparking significant changes to the district's food service program, including...
frankfort-park-district.1

Frankfort Park District Awaits State Agreement on DCEO Grant Amid Public Interest

Frankfort Park District Meeting | September, 2025 Article Summary: Frankfort Park District commissioners are fielding questions from residents about a state grant, with some suggesting the funds be used for the...
Universities respond to new federal Grad PLUS loan caps

Universities respond to new federal Grad PLUS loan caps

By Esther WickhamThe Center Square Santa Clara University School of Law will guarantee $16,000 annual scholarships starting next fall, fully covering tuition following the new federal Grad PLUS loan caps...