Frankfort Board Awards $551,755 in Engineering Contracts for Aberdeen Bridge Replacement
Frankfort Village Board Meeting | March 16, 2026
Article Summary: Following emergency shoring improvements, the Village Board approved structural and design engineering contracts to fully replace the Aberdeen Bridge over Hickory Creek in the Prestwick Subdivision.
Aberdeen Bridge Replacement Key Points:
-
HW Lochner, Inc. was awarded a $400,755.00 contract for structural engineering services.
-
Robinson Engineering, Ltd. was awarded a $151,000.00 contract for design and coordination services.
-
The bridge recently required temporary emergency shoring and needs full replacement in the next two to three years.
The Frankfort Village Board on Monday, March 16, 2026, approved two professional engineering services agreements totaling $551,755.00 to guide the upcoming replacement of the Aberdeen Bridge over Hickory Creek.
The bridge, located within the Prestwick Subdivision, recently underwent temporary emergency shoring to keep it open to traffic. However, the temporary nature of those repairs means the entire structure must be replaced in the next two to three years.
To expedite the project, the Village split the engineering duties into two components. HW Lochner, Inc. was awarded a $400,755.00 contract to handle the structural engineering of the replacement bridge itself. Their scope includes preparing an Abbreviated Bridge Condition Report (ABCR) and delivering full Plans, Specifications, and Estimates (PS&E) for the Illinois Department of Transportation (IDOT).
Robinson Engineering, Ltd. was awarded a $151,000.00 contract to oversee the civil and design engineering. Robinson’s scope includes hydraulic modeling to ensure the new bridge meets floodway construction standards, roadway approach design, maintenance of traffic plans, and coordination with subconsultants for required wetland and geotechnical services.
According to a village memo, design engineering work is anticipated to begin immediately, with bidding targeted for late 2026 or early 2027. Construction is expected to commence in 2027. The Village plans to utilize Motor Fuel Tax (MFT) funds to support the project, with the total estimated bridge cost reaching approximately $3.5 million.
The contracts were approved unanimously as part of the Village Board’s consent agenda.
Latest News Stories
‘Plaintiffs’ lawyer paradise:’ IL lawsuit-friendly courts jack up costs, report says
AG candidate seeks to reform SAFE-T Act
Op-Ed: Senate Bill 3070 provides sensible solution for students, manufacturers
Illinois millionaire’s tax moves closer to November ballot
Illinois Quick Hits: Pritzker issues order to ban state workers from insider trading
Oldest preserve expansion pushes acreage past 24,000 milestone
Virginia voters approve redistricting amendment, potentially flipping 4 seats
WATCH: Millionaire tax critic says AGO, Dems played politics instead of protecting residents
IL Supreme Court can’t just oust judges over speech: New filing
Illinois Republicans say Dems’ redistricting amendment would create more corrupt maps
Vote postponed on Southwest congressmen’s wildfire bill
Trump’s $1.5 trillion military budget: What taxpayers are getting