Frankfort Board Awards $551,755 in Engineering Contracts for Aberdeen Bridge Replacement

Spread the love

Frankfort Village Board Meeting | March 16, 2026

Article Summary: Following emergency shoring improvements, the Village Board approved structural and design engineering contracts to fully replace the Aberdeen Bridge over Hickory Creek in the Prestwick Subdivision.

Aberdeen Bridge Replacement Key Points:

  • HW Lochner, Inc. was awarded a $400,755.00 contract for structural engineering services.

  • Robinson Engineering, Ltd. was awarded a $151,000.00 contract for design and coordination services.

  • The bridge recently required temporary emergency shoring and needs full replacement in the next two to three years.

The Frankfort Village Board on Monday, March 16, 2026, approved two professional engineering services agreements totaling $551,755.00 to guide the upcoming replacement of the Aberdeen Bridge over Hickory Creek.

The bridge, located within the Prestwick Subdivision, recently underwent temporary emergency shoring to keep it open to traffic. However, the temporary nature of those repairs means the entire structure must be replaced in the next two to three years.

To expedite the project, the Village split the engineering duties into two components. HW Lochner, Inc. was awarded a $400,755.00 contract to handle the structural engineering of the replacement bridge itself. Their scope includes preparing an Abbreviated Bridge Condition Report (ABCR) and delivering full Plans, Specifications, and Estimates (PS&E) for the Illinois Department of Transportation (IDOT).

Robinson Engineering, Ltd. was awarded a $151,000.00 contract to oversee the civil and design engineering. Robinson’s scope includes hydraulic modeling to ensure the new bridge meets floodway construction standards, roadway approach design, maintenance of traffic plans, and coordination with subconsultants for required wetland and geotechnical services.

According to a village memo, design engineering work is anticipated to begin immediately, with bidding targeted for late 2026 or early 2027. Construction is expected to commence in 2027. The Village plans to utilize Motor Fuel Tax (MFT) funds to support the project, with the total estimated bridge cost reaching approximately $3.5 million.

The contracts were approved unanimously as part of the Village Board’s consent agenda.

Leave a Comment





Latest News Stories

Illinois quick hits: State rep. appointed circuit judge; Bailey to seek rematch with Pritzker

Illinois quick hits: State rep. appointed circuit judge; Bailey to seek rematch with Pritzker

By Jim Talamonti | The Center SquareThe Center Square State rep. appointed circuit judge Justice Mary K. O’Brien and the Illinois Supreme Court have announced the appointment of state Rep....
WATCH: IL governor on photo with wanted suspect: 'No way to vet everybody'

WATCH: IL governor on photo with wanted suspect: ‘No way to vet everybody’

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker is defending the use of taxpayer dollars for community violence intervention, even after he...

Illinois quick hits: Constitutional amendment would guarantee parental rights

By The Center SquareThe Center Square Constitutional amendment would guarantee parental rights Illinois U.S. Rep. Mary Miller has filed a constitutional amendment to what her office says would permanently establish...

WATCH: Republican leader: says Pritzker budget cut EO a ploy for IL tax increases

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker blames President Donald Trump for ordering Illinois state agencies to find 4% budget cuts....
Judge’s questions during IL gun ban arguments gives rights advocates ‘hope’

Judge’s questions during IL gun ban arguments gives rights advocates ‘hope’

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – With Illinois’ gun ban now in the hands of a three judge panel of the federal appeals...
Illinois agencies to post monthly investment reports, lawmaker calls symbolic

Illinois agencies to post monthly investment reports, lawmaker calls symbolic

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois agencies must now post monthly reports on how taxpayer dollars are invested, a move supporters...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Joliet-Junior-college.-Graphic-Logo.3

JJC Board Approves Student Trustee Quorum Policy Amid Heated Debate

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees passed a controversial policy change allowing the student trustee to be counted...
Meeting Briefs

Meeting Summary and Briefs: Summit Hill School District 161 for August 13, 2025

The Summit Hill District 161 Board of Education on Wednesday, August 13, 2025, approved a major technology contract and navigated a rare split vote on a new teacher hire. The...
Joliet-Junior-college.-Graphic-Logo.2

Joliet Junior College, City of Joliet to Explore Joint Public Safety Institute

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved an intergovernmental agreement with the City of Joliet to begin...
frankfort-school-district-161.2-e1754272831494

Summit Hill 161 Accepts a Dozen Resignations, Approves New Hires

Article Summary: The Summit Hill School District 161 Board of Education processed a significant number of staff changes, accepting twelve resignations and approving a slate of new hires for the 2025-2026...
summit-hill-junior-high-school-frankfort-161

Summit Hill 161 Approves $48K Tech Upgrade, Board Divided on New Teacher Hire

Article Summary: The Summit Hill District 161 Board of Education approved a five-year, $48,305 agreement for a virtual server upgrade and separately hired a new junior high teacher in a contentious...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Village Board for September 8, 2025

The Frankfort Village Board's meeting on Monday, September 8, 2025, was highlighted by a resident's pointed questions regarding the village's process for exploring a potential switch to Lake Michigan water....
Frankfort Village Board Meeting Graphic

Frankfort Resident Questions Village’s Lake Michigan Water Survey Process

Article Summary: A Frankfort resident publicly questioned the village's handling of a recent water source survey during the village board meeting, arguing it was released with limited research and a...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Public Library District for July 24, 2025

The Frankfort Public Library District board on Thursday, July 24, 2025, addressed a major loan payment error by its bank, paused a planned reading room project due to high costs,...