Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township
Will County Public Works and Transportation Committee Meeting | March 3, 2026
Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to “D” Construction for a complete bridge replacement over Forked Creek.
Scheer Road Bridge Key Points:
-
The $1,596,116.16 contract was awarded to Coal City-based “D” Construction, Inc.
-
The project involves the removal of the existing bridge and construction of a new single-span concrete beam bridge.
-
The work on Scheer Road over Forked Creek is located in Green Garden Township (County Board Districts 2 and 3).
-
Construction will require a full roadway closure from April through September 2026.
The Will County Public Works and Transportation Committee on Tuesday, March 3, unanimously confirmed the award of a massive infrastructure contract to replace the aging Scheer Road bridge in Green Garden Township.
The $1,596,116.16 contract was awarded to “D” Construction, Inc., out of Coal City, which submitted the lowest qualified bid during the February 18 letting. The project will be funded through a combination of the Road District’s allotment of Motor Fuel Tax (MFT) funds and County Bridge Tax funds.
The comprehensive project (Section 21-07104-02-BR) will take place on Scheer Road over Forked Creek, impacting County Board Districts 2 and 3.
According to the project summary provided in the agenda packet, the scope of work consists of the complete removal of the existing bridge structure. In its place, crews will construct a new single-span concrete beam bridge. The project also entails installing new full-depth hot-mix asphalt pavement approaching the bridge, reconstructing the aggregate approach chip and seal north of the bridge, and adding new aggregate shoulders, guardrails, and riprap.
The road will be completely closed during the construction period. Work is estimated to begin in April 2026, with an estimated completion date of September 25, 2026.
The committee passed the resolution confirming the award without opposition.
Latest News Stories
State of the College: President Namuo Pushes for Bachelor’s Degrees, Cites Record Graduation Rates
Emergency Freezer Replacement Approved for Adult Detention Facility
California attorney general sues over alleged FERPA violation
California attorney general, Homeland Security debate mask ban
TVA to keep two coal-fired power plants operating indefinitely
Lawmakers probe nationwide child care fraud
Cornyn files Defeat Sharia Law in America Act, another Texas-led effort
WATCH: Attorney cites positive impact of corruption trials 1 year after Madigan conviction
Illinois Quick Hits: $10M scheme alleged in heath care fraud case
WATCH: Trump terminates Obama-era climate change policy
Democrats tank DHS bill again, likely triggering partial govt shutdown
GOP governor candidate Heidner wants Illinois to ‘make,’ not ‘take’