Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Frankfort Meeting 8.4.25

Frankfort to Implement 1% Grocery Tax, Replacing State Levy to Preserve Revenue

FRANKFORT – Frankfort residents will see no change at the grocery checkout line, but the village will preserve a key revenue stream after the Village Board approved an ordinance Monday...
frankfort village hall graphic logo.1

Frankfort to Sell Vacant Downtown Property Valued at $325,000 for Commercial Redevelopment

FRANKFORT – The Village of Frankfort is officially putting a prime piece of vacant, village-owned land in its historic downtown up for sale, aiming to spur immediate commercial redevelopment. The...
frankfort village hall graphic logo.8

New Sushi Restaurant ‘The Orange Hat’ Approved for Frankfort

FRANKFORT – A new full-service sushi restaurant, The Orange Hat, is set to open in the Hickory Creek Market Place after the Village Board approved a special use permit for...
frankfort village hall graphic logo.7

Village Board Approves Zoning Variances for New Custom Home on Bowen Street

FRANKFORT – The Frankfort Village Board on Monday approved two zoning variances for a new custom home at 50 E. Bowen Street, allowing the builder to use non-masonry siding and...
Meeting-Briefs

Meeting Summary: Frankfort Village Board for August 4, 2025

The Frankfort Village Board met on Monday, August 4, 2025, to address several key ordinances and conduct village business. The board approved a measure to replace the state's expiring 1%...
Fire-Ambulance-Rescue-Logo

Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash

The Will County Coroner’s Office has officially identified the woman killed in Tuesday’s fatal crash on Wilmington-Peotone Road as 70-year-old Judith L. Stirm of Delphi, Indiana. In a statement, Coroner...
Frankfort-Police-Rescue

Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond

A person experiencing a mental health crisis was safely rescued from a pond near 80th Avenue in Lakeview Estates on Wednesday after a coordinated response by multiple emergency agencies. Frankfort...
Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a...
Meeting-7.28.25

IT Consultant Urges Green Garden Township to Adopt Modern Cybersecurity Measures

Green Garden Township’s digital infrastructure is vulnerable to cybercrime and requires an immediate overhaul, including adopting a modern, secure email system and multifactor authentication, an IT consultant told the board...
Meeting-Briefs

Meeting Summary and Briefs: Frankfort Township Board for June 9, 2025

The Frankfort Township Board on Monday, June 9, 2025, approved its primary financial documents for the upcoming fiscal year, passing separate and balanced budget appropriation ordinances for the township and...
Sanchez

Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property

Article Summary: Developer Luis Sanchez, a key figure in Monee's commercial growth for two decades, presented a plan to revitalize an industrial property on Industrial Drive. The project, which includes...
Screenshot-2025-08-13-at-2.15.28-PM

Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Article Summary: The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a...
Screenshot-2025-08-13-at-2.11.44-PM

Sheepdog Firearms Gets Green Light for Special Use Permit in Monee

Article Summary: Sheepdog Firearms received final approval from the Monee Village Board for a special use permit to operate a retail and firearms range facility at 25812 S. Sunset Drive....
Wintrust-Crossroads-Sports-Complex

New Lenox Prepares for Grand Opening of Wintrust Crossroads Sports Complex

NEW LENOX – After months of anticipation and intensive work, the New Lenox Community Park District is making final preparations for the grand opening of its flagship Wintrust Crossroads Sports...
New-Lenox-School-122.2

New Lenox D122 Board Approves Tentative Budget, Sets September Public Hearing

The New Lenox School District 122 Board of Education has approved a tentative budget for the 2025-2026 fiscal year, maintaining its long-standing practice of balanced budgets funded by existing cash...