Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates
Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026
Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.
Facilities Key Points:
-
Repair Cost: The final repair bill is estimated between $18,000 and $20,000.
-
Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.
-
In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.
-
Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.
JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.
During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.
“I think it was about $18,000 to $20,000,” Fern said.
Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.
“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”
Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.
In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.
“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.
By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.
Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.
Latest News Stories
Op-Ed: 340B needs transparency to fulfill Its mission
India’s Reliance says it will abide with sanctions on Russian oil purchases
Critics warn Illinois’ ‘megaproject’ tax breaks shift costs to taxpayers
WATCH: Pritzker creates accountability commission amid increased immigration enforcement
Illinois quick hits: Report: $17,300 state debt per person; Metro East crime suppression operations
Trump suspends trade talks with Canada over Ronald Reagan ad
Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for October 16, 2025
WATCH: GOP leader calls Pritzker’s accountability commission a ‘political stunt’
Battery storage financials remain in question as lawmakers consider energy omnibus
Illinois quick hits: Pritzker praises credit upgrade; Cook County approves $20M quantum grant
Op-Ed: Main Street businesses, customers would bear brunt of a tax on services
WATCH: Illinois leaders on both sides send Bailey family condolences for loss of 4