will county board meeting.6

Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates

Spread the love

Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026

Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.

Facilities Key Points:

  • Repair Cost: The final repair bill is estimated between $18,000 and $20,000.

  • Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.

  • In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.

  • Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.

JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.

During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.

“I think it was about $18,000 to $20,000,” Fern said.

Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.

“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”

Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.

In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.

“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.

By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.

Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.

⚠️ Hydrologic Outlook issued June 16 at 2:13PM CDT by NWS Chicago IL
⚠️ Hydrologic Outlook issued June 16 at 2:12PM CDT by NWS Chicago IL
Today Jun 15
Partly Cloudy
54°

Partly Cloudy

Leave a Comment





Latest News Stories

Screenshot 2025-11-06 at 4.17.15 PM

Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: Will County’s federal lobbyists reported that the ongoing government shutdown, now the longest in U.S. history, is...
Screenshot 2025-11-05 at 3.38.44 PM

Frankfort Board Approves Final Plats for Crystal Brook and Copper Creek Subdivisions

Frankfort Village Board Meeting | November 3, 2025 Article Summary: The Frankfort Village Board approved final plats for two major residential developments on Monday, November 3, 2025, advancing plans for...
Will County Logo Graphic

Commission Approves Mokena-Area Garage Variance Over Village’s Objection

Will County Planning and Zoning Commission Meeting | November 4, 2025 Article Summary: The Will County Planning and Zoning Commission approved a variance for a new garage in unincorporated Frankfort Township...
Screenshot 2025-11-05 at 4.02.49 PM

Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Receives Surprise $1.9 Million from IRS Employee Retention Credit

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College has received an unexpected $1.9 million windfall from the federal Employee Retention Credit (ERC), a...
Joliet-Junior-college.-Graphic-Logo.2

JJC Advances ERP Modernization with New Vendor and Two-Year Budget

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryJoliet Junior College is entering the next phase of its Enterprise Resource Planning (ERP) system overhaul, with the...
frankfort-square-park-district.1

Park District Reviews Emergency Response After Frankfort Square Shelter-in-Place

Frankfort Square Park District Meeting | September 2025 Article Summary: Following a law enforcement incident that prompted a shelter-in-place order in Frankfort Square, the park district reviewed its emergency protocols...
Screenshot 2025-11-06 at 4.17.02 PM

Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health

Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025 Article Summary: The Will County Legislative Committee advanced key priorities for its 2026 state and federal legislative agendas, focusing...
solar panels photovoltaics in solar farm

Frankfort Library Board Moves to Explore Community Solar Power

Frankfort Public Library District Meeting | September 2025 Article Summary: The Frankfort Public Library District is exploring renewable energy options after the Board of Trustees authorized a consultant to seek...
Congressional Perks: Committees, caucuses cost $50 million since 2019

Congressional Perks: Committees, caucuses cost $50 million since 2019

By Arthur KaneThe Center Square Since 2019, partisan and special interest caucuses and coalitions in the U.S. House spent at least $50 million for staff, food, travel and other expenses,...
Joliet-Junior-college.-Graphic-Logo.4

JJC Authorizes Land Buy for Grundy County Expansion, Secures Site in Morris

Joliet Junior College Board of Trustees Meeting | October 15, 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees has authorized negotiations for a land acquisition to build a...
FAA funding problems hit airports in California, elsewhere

FAA funding problems hit airports in California, elsewhere

By Madeline ShannonThe Center Square As Christine Finch helped her father, Graham Finch, gather his luggage at the San Francisco International Airport, she was worried about how flight delays caused...
Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

Judge bars ICE from acting against ‘protestors,’ ‘rapid response’ activists

By Jonathan Bilyk | Legal NewslineThe Center Square A Chicago federal judge has barred federal agents from U.S. Border Patrol and ICE from conducting crowd control actions anywhere in northern...
Report: IL public schools show low academic proficiency, higher taxpayer funding

Report: IL public schools show low academic proficiency, higher taxpayer funding

By Jim Talamonti | The Center SquareThe Center Square (The CEnter Square) – The latest education statistics indicate stagnant proficiency for public school students in Illinois, despite dramatic increases in...
Watchdog: Special interest group paid legislators’ $25,000 resort bill

Watchdog: Special interest group paid legislators’ $25,000 resort bill

By Elyse ApelThe Center Square A government watchdog group has filed ethics complaints against more than a dozen Democratic legislators in Colorado. Common Cause alleges the legislators had $25,000 in...