Article Summary: The Summit Hill School District 161 Board approved a contract with RB Crowther Roofing to resurface specific sections of the Mary Drew Early Learning Center and Administration Center. The decision aligns with a long-term facility maintenance plan designed to spread large capital expenses over multiple fiscal years.
Roofing Contract Key Points:
-
Winning Bidder: RB Crowther Roofing was awarded the contract as the lowest responsible bidder among eight companies.
-
Contract Cost: The base bid approved was $242,570.
-
Scope of Work: The project includes resurfacing roof sections 1, 13, and 14 at the Mary Drew facility.
-
Strategy: The board is addressing roof replacements in sections based on warranty expiration dates to remain fiscally responsible.
FRANKFORT — The Summit Hill School District 161 Board of Education on Tuesday, January 21, 2026, authorized a $242,570 contract to repair aging roof sections at the Mary Drew Early Learning Center and Administration Center.
The board selected RB Crowther Roofing following a public bid opening on January 6 that attracted eight contractors. RB Crowther was identified as the lowest responsible bidder.
The project will focus on resurfacing sections 1, 13, and 14 of the building’s roof. Facilities Manager Walter Bruckner III explained that the district manages over 440,000 square feet of roofing and must tackle replacements incrementally to manage the budget.
“When we plan it in pieces, we can be very proactive, long-term sustainable, and fiscally responsible,” Bruckner told the board.
The approved work targets sections where warranties are expiring in 2026. Bruckner indicated that additional sections at Mary Drew—specifically sections 4, 5, and 6—are slated for attention in the following summer.
Board Member Patrick Oliphant expressed support for the segmented approach. “I think it makes it more fiscally responsible when we take sections of the roof and do sections at a time instead of doing a whole roof at one time,” he said.
Bruckner confirmed that he vetted the lowest bidder, speaking directly with RB Crowther representatives to ensure the scope of work was fully understood despite their bid being significantly lower than some competitors.
Latest News Stories
Capital Imp Committee: Begins Drafting Policy to Regulate Artificial Intelligence in County Government
Public Health Committee Chair Demands Animal Control Agreements for Crete, Monee
Public Works Committee Considers Taking Over Kankakee County Line Road to Expedite Bridge Repairs
Peotone Man Charged With Disorderly Conduct, Criminal Damage at New Lenox Target
Executive Committee: Update to Land Resource Management Plan; Solar Farms and Rural Zoning Dominate Discussion
Will County Committee Adds Path to Citizenship Support to Federal Agenda
Health Department Outlines Major Reduction in Consensus Vaccine Schedule
Public Works Committee Forwards Condemnation Proceedings for Francis and Marley Road Improvements
Finance Committee: Scholarship Tax Credit Discussion Halts
Will County Health Department Reports Rise in Respiratory Illnesses, Updates on Facility Issues
Public Works Committee Delays Vote on State Police License Plate Cameras Amid Privacy Concerns
Meeting Summary and Briefs: Frankfort School District 157-C for Nov. 2025