will county board meeting graphic.5

Prairie View Landfill Expansion Plans Take Shape as Consultants Navigate Design Challenges

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: Geologic Associates presented a detailed status update on the proposed expansion of the Prairie View Landfill, outlining a dual approach that includes both vertical and horizontal growth. Consultants revealed a complex engineering solution involving a diversion berm and pulley system to manage leachate collection as new cells are constructed over existing infrastructure.

Landfill Expansion Key Points:

  • Expansion Strategy: The county is pursuing both vertical (upward) and horizontal (outward) expansion simultaneously.

  • Engineering Challenge: A significant hurdle involves maintaining leachate collection from the existing landfill while building new cells on top of it. Consultants designed a 94-foot-wide phase delineation berm and a “pipe within a pipe” pulley system to address this.

  • Soil Pile Obstacle: A large soil stockpile remains on site without a current plan for relocation, necessitating the dual-track design approach. Discussions with neighboring Local 150 regarding land acquisition have stalled but may be restarted.

The Will County Board Landfill Committee received a comprehensive update on Tuesday, January 13, 2026, regarding the ongoing design and planning for the Prairie View Landfill expansion.

Marty Fallon of Geologic Associates, the county’s landfill consultant, presented the latest engineering schematics, highlighting the project’s complexity. The expansion strategy involves a “piggyback” design where new landfill cells will be constructed partially on top of the existing waste mound.

“One of the challenges that we’ve had here with this horizontal expansion… we’re going to cover up a portion of the existing landfill,” Fallon explained. This creates a conflict with the existing leachate collection sumps.

To solve this, consultants have designed a massive 94-foot-wide “phase delineation berm” to separate the old and new sections. Within this berm, they plan to install a specialized diversion system featuring a 24-inch pipe housing a smaller 12-inch pipe with a pulley mechanism. This “straw within a straw” design will allow pumps to be retrieved for maintenance even after they are buried under tons of new waste.

Fallon also addressed a critical logistical issue: a large soil stockpile currently occupying space needed for the horizontal expansion. “Currently we don’t have a plan to move that,” Fallon stated, noting that off-site relocation is required.

This issue sparked discussion about reviving negotiations with Local 150, which owns adjacent property. Chuck Helston, outside counsel for the county, confirmed that previous confidential discussions had stalled but expressed willingness to re-engage at the committee’s direction.

Committee Chair David Oxley suggested a creative solution for the union: “Perhaps they could use that as training for their employees and their apprentices to move that dirt to that pile.” Helston agreed to raise the idea again.

The expansion is not expected to disrupt operations at the adjacent Renewable Natural Gas (RNG) plant. “It won’t be any disruption to the [RNG plant] none,” Fallon assured the committee.

Today Jun 6
Partly Sunny then Chance Showers And Thunderstorms
84° 69°

Partly Sunny then Chance Showers And Thunderstorms

💨 10 mph 💧 51%

Leave a Comment





Latest News Stories

New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
frankfort fire district graphic logo.6

Frankfort Fire District Explores Hiring Consultant for Community Outreach, Potential Referendum

Article Summary: The Frankfort Fire Protection District is considering hiring a consulting firm to enhance its community outreach and gauge public support for a potential future referendum. Trustees heard a...
New-Lenox-Police.3

New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio

NEW LENOX – The local dining scene is set for a boost after the Village Board on Monday approved plans for a new hot dog stand and an outdoor patio...
Meeting-Briefs

Meeting Summary: New Lenox Park District for June 18, 2025

The New Lenox Community Park District Board of Commissioners met on June 18, 2025, to approve its annual budget, advance key park projects, and hear updates on a wide range...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...
frankfort fire district graphic logo.2

Frankfort Fire District Updates Sick Leave Policy for Non-Union Employees

Article Summary: The Frankfort Fire Protection District has approved updates to its administrative sick leave policy, aligning the benefits for non-union staff with those in the firefighters' collective bargaining agreement....

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...