Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway
Will County Public Works & Transportation Committee Meeting | January 6, 2026
Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying Lorenzo Road over the BNSF Railway. The project, fully funded by BNSF, is critical for safety and serves as a nuclear evacuation route.
Lorenzo Road Bridge Project Key Points:
-
Contractor: “D” Construction, Inc. of Coal City, IL.
-
Bid Amount: $18,872,967.20.
-
Project Scope: Construction of a new grade separation (bridge) to replace the at-grade crossing.
-
Timeline: Construction is estimated to start in February 2026 with completion by November 2027.
The Will County Board Public Works & Transportation Committee on Tuesday, January 6, 2026, confirmed the award of an $18,872,967.20 contract to “D” Construction, Inc. for the construction of a bridge carrying Lorenzo Road (County Highway 80) over the BNSF Railway.
The project is located in County Board District 1. According to Director of Transportation Jeff Ronaldson, the project is being funded entirely by BNSF Railway but administered by the county.
“They are funding the entirety of this project. We have to build it because we’re named in the ICC order and related to the grant, but they will reimburse us in total,” Ronaldson said.
The project addresses a significant bottleneck caused by the BNSF rail yard expansion. Trains often slow down or stop while entering the yard, blocking the crossing for extended periods.
“You got those two-mile trains closing that crossing for a significant amount of time,” Ronaldson explained.
Committee Member Dave Oxley (R-Lockport) noted the road’s importance as an evacuation route for the nearby nuclear power plant. Ronaldson confirmed this factor contributed to the project’s priority.
A temporary runaround road will be constructed to keep traffic flowing during the project. The contract calls for completion by November 19, 2027.
Latest News Stories
New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community
Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs
D122 to Spend $24,950 on Professional Enrollment Forecast
Frankfort Library Secures $83K Grant for Reading Room, Financial Report Shows Strong Position
Frankfort Library Considers Limiting Digital Access on Educator Cards to Manage Costs
Newly Appointed Trustee Brooks Stenoish Takes Oath, Finalizing Frankfort Library Board
Meeting Summary: Frankfort Public Library District for June 26, 2025
JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement
Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position
JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate
District 210 Approves Administrative Restructuring, Staff Salary Increases
JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct