Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

Spread the love

A federal judge has given a green light for construction to resume on New York’s largest offshore wind project that was abruptly shut down by the Trump administration last month.

In a ruling issued Thursday, U.S. District Court judge Carl Nichols granted Empire Offshore Wind LLC a preliminary injunction that allows construction activities to resume on the wind project while he considers the broader legal challenge by the company. It’s the second ruling in a week blocking the Trump administration’s effort to stop several offshore wind projects.

In a statement, Norway-based Equinor said it looks forward to resuming construction of the Empire Wind I project, which, when completed, will provide enough energy to power 500,000 homes and “deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand.”

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said. “In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.”

The Interior Department did not immediately respond to a request for comment.

In its legal challenge, Equinor said the Interior Department’s stop-work order is “unlawful” and threatens the progress of ongoing work with significant implications for the project, which is nearly 60% complete.

President Donald Trump has pledged to end federal support for wind and other clean energy projects as he focuses on boosting fossil fuel production as part of broader efforts to improve the nation’s energy independence. He and other Republicans argue that the higher energy costs paid by many in the Northeast are being driven in part by the embrace of clean energy policies.

In December, the Interior Department announced it is halting federal leases for Empire and other large-scale offshore wind projects currently under construction. Besides Empire, the halt included Sunrise Wind, Vineyard Wind 1, Revolution Wind off the New England coast and Coastal Virginia Offshore Wind.

Earlier this week, a federal judge allowed the Revolution Wind project to resume construction while a separate legal challenge filed by its developers is considered by the court.

Interior Secretary Doug Burgum cited unspecified national security risks posed by the offshore wind turbines in pausing federal permits for the projects, but said the move is aimed at “protecting” the American people.

But Nichols, a Trump appointee, said in his order that the federal government’s national security concerns didn’t outweigh the “irreparable harm” Empire Wind would suffer if Trump’s order is not paused.

Speaking at an event on Thursday, Hochul praised the ruling and renewed criticism of the Trump administration for issuing the stop-work order just before Christmas, impacting thousands of workers.

“I’m sick and tired of having to go to court time and time and time again to stop these decisions,” she said in remarks. “They’re designed to do nothing other than hurt workers, hurt our states, hurt our economy and hurt our energy future.”

Leave a Comment





Latest News Stories

New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
frankfort fire district graphic logo.6

Frankfort Fire District Explores Hiring Consultant for Community Outreach, Potential Referendum

Article Summary: The Frankfort Fire Protection District is considering hiring a consulting firm to enhance its community outreach and gauge public support for a potential future referendum. Trustees heard a...
New-Lenox-Police.3

New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio

NEW LENOX – The local dining scene is set for a boost after the Village Board on Monday approved plans for a new hot dog stand and an outdoor patio...
Meeting-Briefs

Meeting Summary: New Lenox Park District for June 18, 2025

The New Lenox Community Park District Board of Commissioners met on June 18, 2025, to approve its annual budget, advance key park projects, and hear updates on a wide range...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
New-Lenox-School-122.3

New Lenox School District 122 Honors State Track and Field Athletes

New Lenox School District 122 took time during its June 17 board meeting to celebrate the outstanding achievements of its junior high athletes at the 2025 IESA State Track and...
frankfort fire district graphic logo.2

Frankfort Fire District Updates Sick Leave Policy for Non-Union Employees

Article Summary: The Frankfort Fire Protection District has approved updates to its administrative sick leave policy, aligning the benefits for non-union staff with those in the firefighters' collective bargaining agreement....

Fiber Optic Internet Competition Coming to New Lenox

NEW LENOX – Residents may soon have a new choice for high-speed internet, as Champaign-based Pavlov Media announced its intention to build out a fiber optic network across the village....
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...
New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...
Meeting-Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...