Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

Spread the love

A federal judge has given a green light for construction to resume on New York’s largest offshore wind project that was abruptly shut down by the Trump administration last month.

In a ruling issued Thursday, U.S. District Court judge Carl Nichols granted Empire Offshore Wind LLC a preliminary injunction that allows construction activities to resume on the wind project while he considers the broader legal challenge by the company. It’s the second ruling in a week blocking the Trump administration’s effort to stop several offshore wind projects.

In a statement, Norway-based Equinor said it looks forward to resuming construction of the Empire Wind I project, which, when completed, will provide enough energy to power 500,000 homes and “deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand.”

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said. “In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.”

The Interior Department did not immediately respond to a request for comment.

In its legal challenge, Equinor said the Interior Department’s stop-work order is “unlawful” and threatens the progress of ongoing work with significant implications for the project, which is nearly 60% complete.

President Donald Trump has pledged to end federal support for wind and other clean energy projects as he focuses on boosting fossil fuel production as part of broader efforts to improve the nation’s energy independence. He and other Republicans argue that the higher energy costs paid by many in the Northeast are being driven in part by the embrace of clean energy policies.

In December, the Interior Department announced it is halting federal leases for Empire and other large-scale offshore wind projects currently under construction. Besides Empire, the halt included Sunrise Wind, Vineyard Wind 1, Revolution Wind off the New England coast and Coastal Virginia Offshore Wind.

Earlier this week, a federal judge allowed the Revolution Wind project to resume construction while a separate legal challenge filed by its developers is considered by the court.

Interior Secretary Doug Burgum cited unspecified national security risks posed by the offshore wind turbines in pausing federal permits for the projects, but said the move is aimed at “protecting” the American people.

But Nichols, a Trump appointee, said in his order that the federal government’s national security concerns didn’t outweigh the “irreparable harm” Empire Wind would suffer if Trump’s order is not paused.

Speaking at an event on Thursday, Hochul praised the ruling and renewed criticism of the Trump administration for issuing the stop-work order just before Christmas, impacting thousands of workers.

“I’m sick and tired of having to go to court time and time and time again to stop these decisions,” she said in remarks. “They’re designed to do nothing other than hurt workers, hurt our states, hurt our economy and hurt our energy future.”

Leave a Comment





Latest News Stories

Lincoln Way District 210 Achieves Highest Bond Rating in History

Lincoln Way Community High School District 210 has reached its highest-ever bond rating of AA3 from Moody's and A+ from Standard & Poor's, culminating a remarkable recovery from financial challenges...
Screenshot-2025-06-05-at-1.43.56-PM

District Recognizes Outstanding Student Readers in Statewide Program

Lincoln Way Community High School District 210 recognized exceptional students who completed the Read for a Lifetime program, with several achieving the rare distinction of reading 100 books over four...
Screenshot-2025-06-05-at-1.43.14-PM

Board Meeting Shorts

Budget Amendment Approved: The board approved amendments to the fiscal year 2025 budget totaling $121.7 million in revenue and $120.1 million in expenses. Changes primarily reflect bond proceeds and related...
Screenshot-2025-06-05-at-1.43.56-PM-1

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...
Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
lincoln-way-school-district

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln-way-school-district

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...