Federal judge allows New York wind project to proceed

Federal judge allows New York wind project to proceed

Spread the love

A federal judge has given a green light for construction to resume on New York’s largest offshore wind project that was abruptly shut down by the Trump administration last month.

In a ruling issued Thursday, U.S. District Court judge Carl Nichols granted Empire Offshore Wind LLC a preliminary injunction that allows construction activities to resume on the wind project while he considers the broader legal challenge by the company. It’s the second ruling in a week blocking the Trump administration’s effort to stop several offshore wind projects.

In a statement, Norway-based Equinor said it looks forward to resuming construction of the Empire Wind I project, which, when completed, will provide enough energy to power 500,000 homes and “deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand.”

“Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period,” the company said. “In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.”

The Interior Department did not immediately respond to a request for comment.

In its legal challenge, Equinor said the Interior Department’s stop-work order is “unlawful” and threatens the progress of ongoing work with significant implications for the project, which is nearly 60% complete.

President Donald Trump has pledged to end federal support for wind and other clean energy projects as he focuses on boosting fossil fuel production as part of broader efforts to improve the nation’s energy independence. He and other Republicans argue that the higher energy costs paid by many in the Northeast are being driven in part by the embrace of clean energy policies.

In December, the Interior Department announced it is halting federal leases for Empire and other large-scale offshore wind projects currently under construction. Besides Empire, the halt included Sunrise Wind, Vineyard Wind 1, Revolution Wind off the New England coast and Coastal Virginia Offshore Wind.

Earlier this week, a federal judge allowed the Revolution Wind project to resume construction while a separate legal challenge filed by its developers is considered by the court.

Interior Secretary Doug Burgum cited unspecified national security risks posed by the offshore wind turbines in pausing federal permits for the projects, but said the move is aimed at “protecting” the American people.

But Nichols, a Trump appointee, said in his order that the federal government’s national security concerns didn’t outweigh the “irreparable harm” Empire Wind would suffer if Trump’s order is not paused.

Speaking at an event on Thursday, Hochul praised the ruling and renewed criticism of the Trump administration for issuing the stop-work order just before Christmas, impacting thousands of workers.

“I’m sick and tired of having to go to court time and time and time again to stop these decisions,” she said in remarks. “They’re designed to do nothing other than hurt workers, hurt our states, hurt our economy and hurt our energy future.”

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025

Will County Planning and Zoning Commission Meeting | December 2, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission met on December 2, 2025, to consider a variety of...
Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Public Library District Board of Trustees for October 23, 2025

Frankfort Public Library District Board of Trustees Meeting | October 2025 Overall Meeting SummaryThe Frankfort Public Library District Board of Trustees met on Thursday, October 23, 2025, to discuss financial...
frankfort village hall graphic logo.8

Misty Creek Development Approved for Sunroom and Patio Additions

Village of Frankfort Board Meeting | December 1, 2025 Article Summary: The Village Board approved a major change to the Misty Creek Planned Unit Development (PUD), allowing future townhome units...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...
frankfort fire district graphic logo.2

Frankfort Fire Trustees Hold Four-Hour Closed Session on Chief Search

Article Summary: The Frankfort Fire Protection District Board of Trustees convened a special meeting on Monday, December 1, 2025, dedicating nearly four hours to a private closed session regarding the search...
frankfort illinois library logo graphic.1

Library Anticipates Purchasing Delays as Major Distributor Closes

Frankfort Public Library District Board of Trustees Meeting | October 2025 Article Summary: Library Director Amanda Kowalcze informed the board that Baker & Taylor, a major book distributor, is going...
Will County P&Z Logo Planning Zoning

P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission approved variance requests for two properties in Peotone Township, allowing...

Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: A renewal of an agreement allowing license plate reading (LPR) cameras in Peotone passed the Public Works Committee,...
Screenshot 2025-12-04 at 11.39.37 AM

Village Secures $1.6 Million Grant for Laraway and Pfeiffer Road Multi-Use Path

Village of Frankfort Board Meeting | December 1, 2025 Article Summary: Frankfort officials authorized agreements with the Illinois Department of Transportation (IDOT) to utilize over $1.6 million in grant funding...
frankfort illinois library logo graphic.1

Library Board Updates Materials Selection Policy and Reconsideration Process

Frankfort Public Library District Board of Trustees Meeting | October 2025 Article Summary: The Library Board approved revisions to the Materials Selection Policy, formally incorporating the "Library of Things" and...
Screenshot 2025-12-05 at 12.00.30 PM

Joliet Unity Movement Criticizes Board’s Handling of Cannabis Tax Revenue

Will County Board Meeting | December 4, 2025 Article Summary: During public comment, the Joliet Unity Movement denounced a recent board vote that redirected cannabis tax revenue away from community...

Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch...
frankfort village hall graphic logo.7

Online Luxury Car Dealership Approved for Center Road

Village of Frankfort Board Meeting | December 1, 2025 Article Summary: The Village Board granted two Special Use Permits to allow Asad’s Import Auto Sales, Inc. to operate an online-based...
Screenshot 2025-12-05 at 11.56.48 AM

Tensions Flare as Board Members Clash Over Budget Process and Protocol

Will County Board Meeting | December 4, 2025 Article Summary: A special meeting intended to fix a budget error turned contentious as board members traded accusations regarding transparency, meeting conduct,...