Village Awards $399,763 Bid for Nebraska Street Pond Dredging
Frankfort Village Board Meeting | December 15, 2025
Article Summary: The Frankfort Village Board on Monday, Dec. 15, 2025, awarded a contract to KLF Enterprises for the mechanical dredging of the Nebraska Street retention pond. The project is designed to restore the pond’s functional capacity after significant sediment buildup hindered effective water treatment.
Pond Dredging Project Key Points:
-
Contract Award: KLF Enterprises submitted the lowest responsible bid of $399,763.
-
Scope of Work: The project involves pond dewatering, mechanical dredging of approximately 4,550 cubic yards of sediment, and full landscape restoration.
-
Location: The 1.41-acre pond is located at the northeast corner of U.S. Route 45 and Nebraska Street.
-
Completion Deadline: All work is scheduled to be finished by April 30, 2026.
The Frankfort Village Board on Monday, Dec. 15, 2025, authorized a major maintenance project for the Nebraska Street retention pond to address years of sediment accumulation.
Trustee Gene Savaria reported that initial estimates indicated between two and four feet of sediment covering the entire bottom of the 1.41-acre pond. This buildup has reduced the pond’s ability to hold storm water and has negatively impacted its treatment functions.
“Significant sediment buildup has reduced the pond’s functional capacity and inhibited effective treatment,” Savaria told the board.
The village received four bid proposals for the project, with KLF Enterprises of Markham emerging as the lowest responsible bidder. The contract requires the company to handle the disposal of all sediment and perform daily clean-ups of any material tracked offsite during the hauling process.
Project specifications include the installation of erosion control measures and a silt fence to protect the surrounding area. Following the dredging, KLF Enterprises is responsible for restoring the landscape with topsoil, seed, fertilizer, and a straw blanket.
The board’s resolution allows the project to begin immediately, with a total duration of 50 working days anticipated for pumping, dredging, and hauling operations.
Latest News Stories
Universities warn state funding delays are wasting millions in taxpayer investment
Trump seeks 44% increase to boost military budget to $1.5 trillion
Illinois Quick Hits: Loyola student’s alleged killer faces federal firearm charge
U.S. adds 178k jobs in ‘strong’ March report amid Iran conflict
Will County Kicks Off Comprehensive Land Resource Management Plan Update with Focus on Proactive Zoning and Environmental Justice
Infighting and Calls for Resignation Disrupt Will County Board Meeting
Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades
Will County Land Use Committee Splits Votes on Massive Earthrise Solar Projects Amid Intense Public Opposition
Groups react to HHS, EPA flagging microplastics for further study
After $241M verdict vs Prairie Farms, Travelers sued for $2B for ‘bad faith’
National debt over 4x greater than reported, accounting group says
FBI cracks down on alleged $60M hospice fraud in LA County