Screenshot 2025-12-20 at 12.26.58 PM

District 210 Awards $24.4 Million Contract for Major HVAC Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | December 18, 2025

Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.

Mechanical Upgrades Key Points:

  • Total Contract Value: $24,419,400 awarded to BEAR Construction Company.

  • Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.

  • Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.

  • Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.

The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.

District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.

“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”

One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.

Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.

Leave a Comment





Latest News Stories

New-Lenox-Township-Food-Pantry

New Lenox Township Food Pantry Reports Record Demand in May

NEW LENOX – The New Lenox Township Food Pantry experienced a record level of need in May, serving 431 families and 1,107 individuals, according to a report at the June...
NL-VB-July-28

New Lenox to Dedicate Street Honoring Pope Leo XIV, Citing Deep Local Ties

NEW LENOX – The Village of New Lenox is celebrating its unique connection to the newly elected Pope Leo XIV, the first American to lead the Roman Catholic Church, by...
New-Lenox-School-122.7

D122 Renews Insurance Policies for Nearly $490,000

The New Lenox School District 122 Board of Education has renewed its property/casualty and worker's compensation insurance policies for the 2025-2026 school year, with total costs amounting to nearly $490,000....
new-lenox-township.2

New Lenox Township Addresses Cemetery Needs, Appoints New Liaison

NEW LENOX – New Lenox Township is turning its attention to the care and potential expansion of its cemeteries, an effort that will be spearheaded by a newly elected trustee....
New-Lenox-Village-Board.2

New Lenox Police Chief Louis Alessandrini Retires; Sgt. David Nykiel Promoted in Leadership Transition

NEW LENOX – The New Lenox Police Department is undergoing a significant leadership transition as Police Chief Louis Alessandrini retires after 20 years with the village, celebrated with an emotional...
Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
frankfort fire district graphic logo.1

Frankfort Fire District to Purchase Two Used Engines to Address Fleet Gap, Budget Constraints

Article Summary: The Frankfort Fire Protection District is moving forward with a plan to purchase two used fire engines for a combined total of $635,000, a strategic move to bolster...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...
frankfort fire district graphic logo.6

Frankfort Fire District Explores Hiring Consultant for Community Outreach, Potential Referendum

Article Summary: The Frankfort Fire Protection District is considering hiring a consulting firm to enhance its community outreach and gauge public support for a potential future referendum. Trustees heard a...