District 210 Awards $24.4 Million Contract for Major HVAC Upgrades

Spread the love

Lincoln-Way Community High School District 210 Meeting | December 18, 2025

Article Summary: The District 210 Board of Education awarded a $24.4 million bid to BEAR Construction Company for comprehensive mechanical and HVAC upgrades at Lincoln-Way Central and East high schools. The project is funded through life safety bonds approved in 2025 and is scheduled to be executed over the next two summers.

Mechanical Upgrades Key Points:

  • Total Contract Value: $24,419,400 awarded to BEAR Construction Company.

  • Equipment Direct Purchase: An additional $3,750,000 was approved for the direct purchase of mechanical equipment through the OMNIA co-op.

  • Timeline: The majority of the work at Lincoln-Way Central is slated for completion in the summer of 2026, with carryover work at both Central and East in 2027.

  • Budget Status: Total project projections, including fees and equipment, stand at $30,415,862, remaining within the $30,420,000 bond funding.

The Lincoln-Way Community High School District 210 Board of Education on Thursday, Dec. 18, 2025, moved forward with its massive life safety initiative by awarding a $24,419,400 bid for HVAC and mechanical upgrades.

The board selected BEAR Construction Company as the lowest qualified bidder for “Base Bid C,” which covers comprehensive work at both Lincoln-Way Central and Lincoln-Way East. The contract includes several alternates, such as the replacement of controls for existing equipment and the installation of conduit for new ComEd primary conductors at Lincoln-Way East.

District officials worked with DLA Architects to structure the bid process, eventually opting to “sole-source” or direct-purchase certain mechanical units through the OMNIA co-op to ensure proper fit and compliance with existing infrastructure. This equipment purchase, totaling $3.75 million from Thermosystems, was approved in a separate motion.

“We are right on budget in terms of life safety,” Assistant Superintendent Michael Duback told the board. “If there were any sort of unknown costs that exceed the life safety bond total, we will draw from budgeted capital projects funding.”

One remaining variable is the potential cost from ComEd related to switchgear upgrades, which is currently estimated at approximately $15,000.

Director of Buildings and Grounds Charles Welke has already begun scheduling meetings with the construction manager to finalize timelines. The plan prioritizes the bulk of the work at Central during the upcoming summer to minimize disruption to the 2026-27 school year.

Today Jun 14
Mostly Sunny
74° 56°

Mostly Sunny

💨 10 mph 💧 0%

Leave a Comment





Latest News Stories

Americans prepare to spend $1 trillion this holiday shopping season

Americans prepare to spend $1 trillion this holiday shopping season

By Brett RowlandThe Center Square More than half of all Americans plan to buy things over the five-day holiday weekend, the beginning of a retail shopping season with consumers projected...
Gas prices ahead of Thanksgiving holding steady

Gas prices ahead of Thanksgiving holding steady

By Morgan SweeneyThe Center Square The average price of gas has fallen in 2025, and it appears to be mostly holding steady around $3 heading into the Thanksgiving holiday –...
Illinois quick hits: Migrant youth allegedly murdered homeless Chicago man

Illinois quick hits: Migrant youth allegedly murdered homeless Chicago man

By Jim Talamonti | The Center SquareThe Center Square Migrant youth allegedly murdered homeless Chicago man Three juvenile Venezuelan migrants are part of a group that allegedly attacked, murdered, and...

WATCH: Trump calls Pritzker a ‘fat slob,’ Illinois governor blasts president

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – President Donald Trump has revived his criticism of Illinois Gov. J.B. Pritzker over crime, and Pritzker has...
Illinois business group warns of 'backbreaking' progressive income tax

Illinois business group warns of ‘backbreaking’ progressive income tax

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Manufacturers say legislators at the Illinois State Capitol have done enough damage and a progressive tax would...
Illinois tops U.S. in pumpkin production despite recent decline in value

Illinois tops U.S. in pumpkin production despite recent decline in value

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Despite a recent decline in production value, Illinois is far and away the leader when it comes...
Congress moves to restore federal union powers, critics warn of higher costs

Congress moves to restore federal union powers, critics warn of higher costs

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The U.S. Congress is set to vote on House Resolution 2550, a bill that would restore...
Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

By Jim Talamonti | The Center SquareThe Center Square Chiropractor sentenced for fraud A Chicago chiropractor has been sentenced to nearly six years in federal prison for billing a private...
Meeting Briefs

Meeting Summary and Briefs: Village of Frankfort for November 17, 2025

Village of Frankfort Meeting | November 17, 2025 The Frankfort Village Board on Monday, November 17, 2025, approved a series of measures focused on new business development, public safety upgrades,...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Frankfort School District 157-C.2

Frankfort 157-C Implements New Plan to Combat Chronic Student Absenteeism

Frankfort School District 157-C Meeting | October 2025 Article Summary: Frankfort School District 157-C is rolling out a new, detailed attendance support plan aimed at reducing chronic absenteeism, an issue...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...