'Consequential' day ahead for future household electricity costs

‘Consequential’ day ahead for future household electricity costs

Spread the love

(The Center Square) – PJM’s Board of Directors is preparing to make one of the most consequential decisions of this decade, says a coalition of state legislators from the grid operator’s region.

And, depending upon the choice made, it could save households and businesses as much as $70 per month on their utility bills.

On Monday, ahead of a pending Nov. 19 vote on proposals that would determine how data centers should be connected to the grid, the coalition announced it submitted a plan to ensure the 67 million Americans served by PJM will not bear an unfair share of reliability risk and cost driven by soaring data center electricity demand.

The Protecting Ratepayers Proposal came in response to PJM’s Critical Issues Fast Path, or CIFP – an initiative launched in August to fast-track discussions and policy decisions on managing rapid growth of large load customers like data centers.

The proposal builds on a resolution passed by the National Conference of State Legislators and upon elements of others submitted to PJM, including one submitted by the governors of Maryland, Virginia, New Jersey, and Pennsylvania, in partnership with the Data Center Coalition and Exelon.

It also echoes proposals from consumer advocate groups in Pennsylvania and Maryland and has gained the support of the Natural Resources Defense Council, or NRDC, whose original suggestions were included.

During a media briefing on Monday, Democratic DC Councilmember Charles Allen emphasized that the issue impacts everyone, and the coalition’s size and scope highlight what’s at stake. “It’s not very often that leaders from a broad number of states come together in a shared fight,” he added.

Sen. Katie Fry Hester, D-Md., explained that anticipated demand from new data centers is projected to reach 32 GW, with some forecasts suggesting it could grow to 60 GW in the coming years.

“That’s the equivalent of adding a major city like Philadelphia to the grid almost overnight,” she said.

On Wednesday, after reviewing between 16 and 20 proposals, PJM and its members – including utility companies, transmission operators and power generators – then vote on their recommendations to the Board of Directors.

“Data centers should power their profits, not drain the wallets of everyday Americans,” said Sen. Rachel Ventura, a Democrat from Illinois.

Her state, she said, has already started to address the challenge by passing Senate Bill 25, also known as The Clean and Reliable Grid Affordability Act, now awaiting Gov. JB Pritzker’s signature.

The bill invests in battery storage, energy efficiency, and smart grid technologies, Ventura said. It adds 3 GW of storage with no upfront cost to consumers, which can be dispatched at peak time to lower prices and improve reliability. She noted that it’s a strong first step, but Illinois alone cannot solve a regional problem.

“The cost of electricity is expected to skyrocket by over $100 billion through 2033 due to data center load growth, which could cost families and businesses in PJM territory an extra $70 per month,” said Claire Lang-Ree, advocate for the Sustainable FERC Project at NRDC.

Lang-Ree said the coalition’s proposal is one of the few that addresses the difficult question of what happens if there isn’t enough power to go around.

She explained that under their proposal, data centers can join PJM quickly, but they will be interruptible – or the first to be curtailed – unless they bring their own capacity to the grid.

Other key features of the proposal include:

Multiple fast-track options for data centers to bring their own firm power supply through new power plants, demand response, or distributed resources – while preventing them from pulling existing plants from the grid or jumping ahead of renewable projects already in the queue. Load forecasting enhancements to screen out speculative projects for transmission planning.A temporary extension of the capacity market “price collar” to curb further price spikes.

Legislators stressed that while each state faces unique energy challenges, they are united in the shared goal of ensuring ratepayers across the PJM region are not subsidizing the energy costs of new data centers being built by Fortune 500 companies like Google, Amazon, and Microsoft.

Delaware and Maryland have enacted transparency laws requiring public utilities to report how they vote in the PJM Interconnection stakeholder/committee process, according to Sen. Stephanie Hansen, a Democrat from Delaware.

Energy resources are scarce, so competition is fierce, Hansen said.

“It’s the wild wild west when it comes to where data centers will be located. There are few rules, and states are competing against each other for jobs and revenue, “knowing that the cost to feed the energy monster,” as Hansen described it, “will be socialized to other ratepayers in and out of the state.”

She said they encourage PJM to forge a responsible path going forward – and keeping renewable projects at the forefront of interconnection planning is critically important. “This is a marathon, not a sprint,” she said, “and the starting gun has already sounded.”

Leave a Comment





Latest News Stories

Chicago pension, debt services costs among highest in country

Chicago pension, debt services costs among highest in country

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – Chicago’s budget has grown by nearly 40% since 2019 with the biggest increased expenditure going toward...
WATCH: DCFS still looking for missing children numbers; Pritzker on elections results

WATCH: DCFS still looking for missing children numbers; Pritzker on elections results

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop continues his coverage...
Illinois quick hits: DHS ordered to address ICE facility conditions; Garcia explains retirement decision

Illinois quick hits: DHS ordered to address ICE facility conditions; Garcia explains retirement decision

By Jim Talamonti | The Center SquareThe Center Square DHS ordered to address ICE facility conditions A U.S. District Court judge in Chicago has issued a temporary restraining order directing...
Congressional Perks: Luxury cars and mileage result in big costs for taxpayers

Congressional Perks: Luxury cars and mileage result in big costs for taxpayers

By Arthur Kane | The Center SquareThe Center Square (The Center Square) – U.S. Reps Darrell Issa, R-Calif., and David Scott, D-Ga., have each had taxpayers pay as much as...
Frankfort School District 157-C.2

State Assessment Shake-up: Frankfort 157-C to Form Committee for New Honors Criteria

Frankfort School District 157-C Meeting | September 2025 Article Summary: Frankfort School District 157-C is adapting to new, less restrictive student assessment benchmarks from the Illinois State Board of Education...
frankfort fire district graphic logo.2

Frankfort Fire District Adopts Updated Fire Codes to Address Solar Power, New Technologies

Frankfort Fire Protection District Meeting | September 2025 Article Summary: The Frankfort Fire Protection District has unanimously adopted a new fire prevention ordinance to modernize safety standards and address emerging...
Illinois quick hits: $20 million for Alton housing project; alleged migrant assaults reported

Illinois quick hits: $20 million for Alton housing project; alleged migrant assaults reported

By Jim Talamonti | The Center SquareThe Center Square $20 million for Alton housing project Gov. J.B. Pritzker and the Illinois Housing Development Authority announced the opening of a $20...

WATCH: Illinois DCFS can’t locate documents showing number of missing children

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Documents to show the number of missing youth in care from the Department of Children and Family...
Will Dial-A-Ride Service

Will County Committee Advances Phased Takeover of Central Will Dial-A-Ride Service

Will County Public Works & Transportation Committee Meeting | November 2025 Article Summary: The Will County Board approved a five-year plan to consolidate the Central Will Dial-A-Ride service into its...
Frankfort Mcdonalds

Frankfort Board Denies 24-Hour Drive-Thru Permits for McDonald’s

Frankfort Village Board Meeting | November 3, 2025 Article Summary: The Frankfort Village Board on Monday, November 3, 2025, denied special use permits that would have allowed two local McDonald's...
frankfort illinois library logo graphic.1

Frankfort Library Board Approves 2025 Tax Levies

Frankfort Public Library District Meeting | September 2025 Article Summary: The Frankfort Public Library District Board of Trustees has unanimously approved its 2025 tax levy ordinance and a separate building...
Meeting Briefs

Meeting Summary and Briefs: Frankfort Park District Committee for September 23, 2025

Frankfort Park District Special Committee Meeting | September 23, 2025 The Frankfort Park District Committee on Tuesday reviewed results from a community survey about a proposed indoor recreation center, which...
frankfort-square-park-district.2

Hunter Prairie Park Redevelopment on Track, Four-Year Journey Detailed

Frankfort Square Park District Meeting | September 2025 Article Summary: The Frankfort Square Park District's multi-year redevelopment of Hunter Prairie Park is progressing, with a detailed timeline presented at the...
Frankfort School District 157-C.3

Frankfort 157-C Board Approves $47 Million Budget for 2025-2026 School Year

Frankfort School District 157-C Meeting | September 2025 Article Summary: The Frankfort School District 157-C Board of Education unanimously approved a balanced budget for the 2025-2026 fiscal year, projecting total...
frankfort-park-district

Park District Gathers Sports Group Input for State-Funded Master Plan

Frankfort Park District Special Committee Meeting | September 23, 2025 Article Summary: The Frankfort Park District is actively engaging with local sports organizations to gather feedback for its new master plan,...