Will County Public Works & Transportation Committee Meeting | November 2025

Article Summary: The Will County Board approved two key agreements for the Gougar Road bridge project in New Lenox, authorizing over $300,000 for supplemental design engineering and an estimated $240,000 to reimburse Nicor Gas for relocating facilities.

Gougar Road Project Key Points:

  • A supplemental agreement of $301,703 was approved with A. Epstein and Sons International, Inc. for expanded Phase II design engineering services.

  • An agreement was authorized to reimburse Nicor Gas Company for an estimated $240,000 to move its facilities for the Gougar Road (CH 52) bridge project over the CN Railroad.

The Will County Board on Tuesday, November 4, 2025, pushed a major infrastructure project in New Lenox forward by unanimously approving two agreements totaling more than half a million dollars for the proposed Gougar Road bridge over the CN Railroad.

The board authorized a supplemental professional services agreement with A. Epstein and Sons International, Inc. for $301,703. The funds will cover expanded Phase II design engineering services for the project, which is located in County Board District #2. According to project documents, the supplemental work includes redesigning the bridge from a three-span to a four-span structure to avoid relocating an adjacent Nicor facility, extending project limits, and designing a water main relocation for the Village of New Lenox.

In a related action, the board approved a second agreement to reimburse Northern Illinois Gas Company (Nicor) for the actual costs of relocating its gas facilities to accommodate the bridge construction. The estimated cost for Nicor’s work is $240,000. This reimbursement is necessary as Nicor holds a superior right to its existing easement where the county improvements are planned.

Both measures passed without opposition, signaling the board’s continued commitment to the grade separation project, which aims to improve traffic flow and safety on Gougar Road.

Leave a Comment





Latest News Stories

new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting-Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting-Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
New-Lenox-Village-Board.1

New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget

NEW LENOX – The newly opened Crossroads Sports Complex is already proving to be a resounding success, according to a report delivered at the New Lenox Village Board meeting on...
New-Lenox-Village-Board.4

New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects

NEW LENOX – The New Lenox Village Board unanimously approved waiving more than $13,000 in permit and plan review fees for two significant community projects during its meeting on Monday....
New-Lenox-Police.3

New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive

NEW LENOX – The Village Board on Monday approved site modifications for a new truck repair business, MBPRO Services, set to open at 21660 South Moni Drive. The board unanimously...
Meeting-Briefs

Meeting Summary: New Lenox Board of Trustees for July 14, 2025

The New Lenox Village Board of Trustees met Monday to approve site plans for a new business, waive fees for community projects, and hear a glowing report on the new...
Meeting-Briefs

Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for June 10, 2025

The Frankfort Fire Protection District Board of Trustees held a special meeting on June 10 to address two major financial items: the fiscal year budget and a new contract with...
frankfort fire district graphic logo.2

Frankfort Fire District Projects $350,000 Surplus, But Faces Capital Crunch for New Engine

Article Summary: The Frankfort Fire Protection District is on track to end the fiscal year with a $350,000 operating surplus, but officials warn that purchasing a much-needed new fire engine...