Commission Grants Green Garden Solar Farm Project Variance Extension

Spread the love

Will County Planning and Zoning Commission Meeting | November 4, 2025

Article Summary: The Will County Planning and Zoning Commission granted a 180-day extension for two variances related to a commercial solar energy facility in Green Garden Township, allowing the developer to wait for optimal planting conditions in Spring 2026 before proceeding. The variances, originally approved in March, concern the mowing schedule and plant height for the native pollinator habitat required for the project.

Green Garden Solar Farm Key Points:

  • The first-time extension was granted for variances associated with a 35-acre solar project on LaGrange Road near West Manhattan-Monee Road.

  • The variances reduce the required number of mowings from five to one per year and increase the maximum allowed ground cover height from 13 to 36 inches.

  • The developer requested the extension to allow time to prepare the site for planting a native pollinator seed mix in favorable spring conditions.

A commercial solar energy facility planned for Green Garden Township received a procedural timeline extension from the Will County Planning and Zoning Commission on Tuesday, November 4, 2025.

The commission approved a 180-day extension for two variances previously granted to applicant TPE IL WI258, LLC, an affiliate of TPE Development, LLC, for a 35-acre solar farm. The project is located on vacant property at the northeast corner of LaGrange Road and West Manhattan-Monee Road in Monee.

The variances, originally approved by the commission on March 4, 2025, are key to the project’s use of native plantings and agrivoltaics—the simultaneous use of land for agriculture and solar power generation. One variance reduces the required number of mowings from five times per year to just one, while the other increases the maximum allowable plant height from 13 inches to 36 inches. These changes are necessary to establish and maintain a healthy native pollinator habitat on the site, which is a requirement of the state’s community solar program.

According to a memo from county staff, the developer has not yet applied for a building permit because “favorable planting conditions for the site are not expected until after the variances expire on March 4, 2026.” The extension was requested to allow the developer time to prepare the site for planting in the spring of 2026.

The commission, which is authorized to grant up to two 180-day extensions for good cause, approved the request. The variances will now expire on August 31, 2026.

Leave a Comment





Latest News Stories

Wintrust-Crossroads-Sports-Complex

New Lenox Prepares for Grand Opening of Wintrust Crossroads Sports Complex

NEW LENOX – After months of anticipation and intensive work, the New Lenox Community Park District is making final preparations for the grand opening of its flagship Wintrust Crossroads Sports...
New-Lenox-School-122.2

New Lenox D122 Board Approves Tentative Budget, Sets September Public Hearing

The New Lenox School District 122 Board of Education has approved a tentative budget for the 2025-2026 fiscal year, maintaining its long-standing practice of balanced budgets funded by existing cash...
New-Lenox-Township-Food-Pantry

New Lenox Township Food Pantry Reports Record Demand in May

NEW LENOX – The New Lenox Township Food Pantry experienced a record level of need in May, serving 431 families and 1,107 individuals, according to a report at the June...
NL-VB-July-28

New Lenox to Dedicate Street Honoring Pope Leo XIV, Citing Deep Local Ties

NEW LENOX – The Village of New Lenox is celebrating its unique connection to the newly elected Pope Leo XIV, the first American to lead the Roman Catholic Church, by...
New-Lenox-School-122.7

D122 Renews Insurance Policies for Nearly $490,000

The New Lenox School District 122 Board of Education has renewed its property/casualty and worker's compensation insurance policies for the 2025-2026 school year, with total costs amounting to nearly $490,000....
new-lenox-township.2

New Lenox Township Addresses Cemetery Needs, Appoints New Liaison

NEW LENOX – New Lenox Township is turning its attention to the care and potential expansion of its cemeteries, an effort that will be spearheaded by a newly elected trustee....
New-Lenox-Village-Board.2

New Lenox Police Chief Louis Alessandrini Retires; Sgt. David Nykiel Promoted in Leadership Transition

NEW LENOX – The New Lenox Police Department is undergoing a significant leadership transition as Police Chief Louis Alessandrini retires after 20 years with the village, celebrated with an emotional...
Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
frankfort fire district graphic logo.1

Frankfort Fire District to Purchase Two Used Engines to Address Fleet Gap, Budget Constraints

Article Summary: The Frankfort Fire Protection District is moving forward with a plan to purchase two used fire engines for a combined total of $635,000, a strategic move to bolster...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting-Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....