New Lenox Solar Farm Proposal Advances with Conditions, Following Village and Forest Preserve Input

Spread the love

Will County Planning and Zoning Commission Meeting | October 21, 2025

Article Summary: The Will County Planning and Zoning Commission recommended approval for a 62.7-acre commercial solar energy facility in New Lenox Township, contingent on several conditions, including the development of an emergency response plan and adherence to landscaping requests from the Village of New Lenox. The project, proposed by Nexamp Solar LLC, aims to contribute to Illinois’ renewable energy goals under the Climate and Equitable Jobs Act (CEJA).

Spencer Road Solar Farm Key Points:

  • Project Scope: A special use permit was sought for a commercial solar energy facility on a 110-acre property on South Spencer Road, utilizing approximately 62.7 acres for two projects totaling 5.25 MW (AC).

  • Variances Approved: The commission also recommended variances to allow pollinator-friendly ground cover to grow up to 36 inches (from 13 inches) and to reduce the required number of mowings from five to one annually.

  • Local Input: The Village of New Lenox did not object but recommended conditions concerning setbacks, access drive surfacing, fencing, and landscape screening. The Forest Preserve District of Will County also provided recommendations to protect local wildlife.

  • State Law Compliance: The project falls under Illinois Public Law 102-1123, which sets specific parameters and timelines for counties to review commercial solar energy proposals.

JOLIET, IL – The Will County Planning and Zoning Commission on Tuesday, October 21, 2025, recommended approval for a large-scale commercial solar energy facility on approximately 62.7 acres of agricultural land in New Lenox Township. The recommendation, which now goes to the full Will County Board for a final decision, includes a special use permit and two variances aimed at promoting pollinator-friendly habitats on the site.

The project, proposed by developer Nexamp Solar LLC under the names Spencer Road Solar East LLC and Spencer Road Solar West LLC, involves constructing two adjacent solar facilities on a 110-acre property located on South Spencer Road, south of the Village of New Lenox. The combined facilities will feature approximately 12,029 solar panels on single-axis tracker systems, generating a total of 5.25 megawatts (AC).

The proposal is part of the state’s Adjustable Block program under the Climate and Equitable Jobs Act (CEJA), which incentivizes renewable energy projects. According to Illinois law, county review of such projects is subject to a strict timeline, requiring a public hearing within 60 days of a complete application.

In addition to the special use permit, the commission recommended two variances from county code. The first increases the maximum allowed height for ground cover plants from 13 inches to 36 inches. The second reduces the required number of mowings from five times per year to just once. Staff reports indicated these variances are crucial for establishing a “pollinator-friendly solar site” under the Illinois Pollinator-Friendly Solar Site Act. The taller native vegetation and reduced mowing allow deep-rooted pollinator species to propagate, which helps recharge agricultural soils, improve water infiltration, and provide habitat for birds and insects.

The Village of New Lenox, whose corporate boundary is within 400 to 1,300 feet of the property, reviewed the project and did not object. However, the village board recommended five conditions for approval. These include meeting all county setback requirements, installing a concrete or asphalt surface for the access drive within the Spencer Road right-of-way, installing an eight-foot-tall Fixed Knot Farm fence, placing landscape screening along the western fence line, and abiding by all New Lenox Fire Protection District requirements.

The Forest Preserve District of Will County also submitted a letter with recommendations to mitigate environmental impacts. The district suggested installing wildlife-friendly fencing with a six-inch gap at the bottom to allow for animal movement, clearing trees only between November 1st and March 31st to protect wildlife, and using native quality plant species for landscaping.

According to the developer, the site will be remotely monitored 24/7, with employees only visiting occasionally for maintenance. The project is expected to create 20 to 25 local jobs during its estimated six-month construction phase, anticipated to begin in the fall of 2026. The developer has also entered into an Agricultural Impact Mitigation Agreement (AIMA) with the Illinois Department of Agriculture to ensure the preservation of the agricultural land and provide financial assurance for the eventual decommissioning of the facility.

Leave a Comment





Latest News Stories

frankfort illinois library logo graphic.5

Frankfort Library Board Appoints Former Trustee Brooks Stenoish to Fill Vacancy

The Frankfort Public Library District Board of Trustees on Tuesday appointed former trustee Brooks Stenoish to fill a vacant seat, bringing an experienced member back into the fold just weeks...
frankfort illinois library logo graphic.1

Meeting Summary: Frankfort Public Library District for June 17, 2025

The Frankfort Public Library District Board of Trustees held a special meeting on Tuesday, where its primary actions were to fill a board vacancy and conduct an orientation for its...
Will-County-Board-Meeting-June-18-2025

Will County Board Halts Transportation Plan After Contentious 143rd Street Debate

The Will County Board voted Wednesday to send its five-year, multi-million dollar transportation improvement plan back to committee, effectively pausing all projects after a lengthy and heated debate over the...
Will-County-Board-Meeting-June-18-2025

Will County Board Upholds Zoning Denials, Rejecting Developer Appeals

The Will County Board on Wednesday backed its Planning and Zoning Commission (PZC), denying two separate appeals from property owners who sought to overturn the commission’s recommendations against their projects....
Will-County-Board-Meeting-June-18-2025

Split Vote Halts Monee Truck Terminal Project

A proposed truck terminal on vacant land at West Monee-Manhattan Road in Monee Township was stopped in its tracks Wednesday after the Will County Board delivered a split decision on...
Will-County-Board-Meeting-June-18-2025

Future Quarry Fight Looms as Board Approves ‘Tequila Barrel’ Retreat

While the Will County Board greenlit a unique tourist destination featuring overnight stays in repurposed tequila barrels, it also received formal notice of a coming fight to shut down a...
Meeting-Briefs

News Briefs from the Will County Board June 18 Meeting

Monee Church Designated Historic LandmarkThe Will County Board unanimously voted to designate St. Paul's United Church of Christ in Monee as a historical landmark. Member Judy Ogalla, a Monee native,...
frankfort village hall graphic logo.1

Frankfort Approves Outdoor Patios for The Loft and Grounded Coffee Bar, Waives All Parking Requirements

Downtown Frankfort is set to expand its outdoor dining options after the Village Board on Monday approved plans for new patios at two adjacent businesses, The Loft and Grounded Coffee...
frankfort village hall graphic logo.7

Frankfort Police Department to Get Four New Vehicles in Fleet Upgrade

FRANKFORT, Ill. – The Frankfort Police Department will be updating its aging fleet after the Village Board approved the purchase of four new vehicles for a total cost not to...
frankfort village hall graphic logo.2

Indoor Pickleball Facility ‘Pickled!’ Gets Green Light in Frankfort

A new indoor pickleball facility named "Pickled!" is set to open in Frankfort after the Village Board granted a special use permit for the business at its Monday meeting. The...
frankfort village hall graphic logo.6

Frankfort to Install Public Wi-Fi at Breidert Green

Visitors to Breidert Green in downtown Frankfort will soon have access to free public wireless internet. The Village Board on Monday approved the purchase and installation of Wi-Fi equipment to...
frankfort village hall graphic logo.1

Frankfort Board Approves Indoor Recreation Facility and Setback Variance

The Frankfort Village Board gave its approval to two separate development projects Monday night, clearing the way for a new indoor pickleball facility and a residential addition. Trustees unanimously granted...
Frankfort-Village-Board-Meeting-Graphic-June-16-2025

Meeting Briefs: Frankfort Village Board for June 16, 2025

Downtown Patios Approved, Parking Waived: The Village Board approved outdoor seating for The Loft and Grounded Coffee Bar on Ash Street. To support the downtown businesses, trustees also voted to waive...
Will-County-Executive-Committee-Meeting-June-12-2025

Mental Health Board Awards $5 Million in Grants to Will County Organizations

The Will County Community Mental Health Board has distributed over $5 million in grants to 39 local organizations, marking the completion of its inaugural funding cycle since voters approved the...
frankfort-square-park-district.2

Frankfort Square Park District Adopts Budget and Appropriation Ordinance, Updates Financial Policy

The Frankfort Square Park District Board of Commissioners formally adopted its Budget and Appropriation Ordinance for the 2025-2026 fiscal year on Thursday, finalizing the district's legal spending authority for the...