Fort Frankfort Playground Grand Opening Delayed Until Spring 2026

Spread the love

Frankfort Park District Meeting | September, 2025

Article Summary: The grand opening of the new Fort Frankfort playground, a highly anticipated community project, has been pushed back to spring 2026 due to delays in receiving properly coated equipment and newly manufactured railings. Park district officials report the project is nearing 90% completion and will likely be finished in the next month, but the official opening will wait until warmer weather returns.

Fort Frankfort Project Key Points:

  • The completion of the Fort Frankfort playground project has been delayed.

  • The cause is the return of pieces that needed re-coating and the ongoing manufacturing of new railings.

  • Executive Director Gina Hassett reported the project should be 90% finished in the next month or so.

  • A grand opening for the new playground is now anticipated for spring 2026.

The grand opening of the new Fort Frankfort playground will be delayed until next spring, Frankfort Park District officials announced at the Board of Commissioners meeting on Tuesday, September 9, 2025.

During her report, Executive Director Gina Hassett provided an update on the major construction project, explaining that issues with equipment have pushed back the final completion date. Hassett noted that several pieces of the playground, including parts of the roof, had to be returned to the manufacturer for re-coating.

“The company is making new railings that will be delivered soon,” Hassett added, citing another factor in the revised timeline.

Despite the setbacks, the project is in its final stages. “90% of the project should be finished in the next month or so,” Hassett reported. However, with colder weather approaching, she stated that a grand opening celebration will likely take place in the spring of 2026 to ensure the community can fully enjoy the new facility upon its debut.

The delay has also impacted other park activities. In the Recreation Report, Superintendent Stacy Proper noted that participation in the Splash Pad this season was down, a trend attributed to the ongoing construction of the adjacent Fort Frankfort playground.

Community support for the new playground continues, with the “Pours for the Parks” fundraising event scheduled for October 18. The event is part of the “Operation Playground” initiative to support park amenities.

Commissioner Tom Ruvoli also acknowledged the community’s enthusiasm for park improvements, thanking the staff for their hard work on the Fall Fest parade and extending the board’s gratitude to everyone who worked at the Splash Park over the summer.

Leave a Comment





Latest News Stories

Screenshot-2025-06-16-at-3.26.08-PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will-county-board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...
will-county-board

Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate

Members seek clarification on requirements that could favor unionized businesses The Will County Board postponed action on proposed changes to county purchasing ordinances after members raised concerns about language that...
frankfort-square-park-district.2

New Frankfort Square Park Board Takes Helm Amid Strong Financials, Maksymiak and Moore Elected Leaders

The Frankfort Square Park District Board of Commissioners seated four new members and re-elected its leadership during a productive annual organizational meeting on May 15, all while celebrating a robust...
will-county-board.2

Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township

Board postpones decision on Torres family request pending barn variance appeal A contentious hearing over Fernando Torres' request to keep horses on his Crete Township property exposed deep neighborhood divisions...
frankfort-square-park-district.1

Park District Awards Eight Scholarships to Lincoln-Way East Seniors

The Frankfort Square Park District awarded $1,000 scholarships to eight graduating seniors from Lincoln-Way East High School at the school’s Community Scholarship Night on May 7. Park Board Commissioners Frank...
will-county-board.3

Transportation Projects Advance as Board Approves Vision Zero, Road Improvements

County adopts traffic safety initiative while funding major infrastructure upgrades The Will County Board approved a comprehensive transportation agenda including adoption of Vision Zero principles and multiple road improvement projects...
County-Board-Room

Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated

Board approves funding increases and policy changes for county health services The Will County Board approved budget appropriations for the health department and updated admission policies for Sunny Hill Nursing...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for May 15, 2025

At its annual organizational meeting, the Frankfort Square Park District Board of Commissioners swore in four members, re-elected its leadership, and reviewed its strong end-of-year financial report. The district’s funds...

Lincoln Way District 210 Achieves Highest Bond Rating in History

Lincoln Way Community High School District 210 has reached its highest-ever bond rating of AA3 from Moody's and A+ from Standard & Poor's, culminating a remarkable recovery from financial challenges...
Screenshot-2025-06-05-at-1.43.56-PM

District Recognizes Outstanding Student Readers in Statewide Program

Lincoln Way Community High School District 210 recognized exceptional students who completed the Read for a Lifetime program, with several achieving the rare distinction of reading 100 books over four...
Screenshot-2025-06-05-at-1.43.14-PM

Board Meeting Shorts

Budget Amendment Approved: The board approved amendments to the fiscal year 2025 budget totaling $121.7 million in revenue and $120.1 million in expenses. Changes primarily reflect bond proceeds and related...
Screenshot-2025-06-05-at-1.43.56-PM-1

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...
Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...