Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Spread the love

Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Leave a Comment





Latest News Stories

Lincoln Way District 210 Achieves Highest Bond Rating in History

Lincoln Way Community High School District 210 has reached its highest-ever bond rating of AA3 from Moody's and A+ from Standard & Poor's, culminating a remarkable recovery from financial challenges...
Screenshot-2025-06-05-at-1.43.56-PM

District Recognizes Outstanding Student Readers in Statewide Program

Lincoln Way Community High School District 210 recognized exceptional students who completed the Read for a Lifetime program, with several achieving the rare distinction of reading 100 books over four...
Screenshot-2025-06-05-at-1.43.14-PM

Board Meeting Shorts

Budget Amendment Approved: The board approved amendments to the fiscal year 2025 budget totaling $121.7 million in revenue and $120.1 million in expenses. Changes primarily reflect bond proceeds and related...
Screenshot-2025-06-05-at-1.43.56-PM-1

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...
Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
lincoln-way-school-district

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln-way-school-district

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting-Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...