Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Spread the love

Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

⚠️ Hydrologic Outlook issued June 16 at 2:13PM CDT by NWS Chicago IL
⚠️ Hydrologic Outlook issued June 16 at 2:12PM CDT by NWS Chicago IL
Tue Jun 16
Showers And Thunderstorms
71° 59°

Showers And Thunderstorms

💨 5 to 20 mph 💧 99%

Leave a Comment





Latest News Stories

Screenshot 2025-12-20 at 12.27.17 PM

Lincoln-Way High Schools Maintain Top State Rankings; EL Progress Jumps

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The 2025 Illinois Report Card data reveals that Lincoln-Way Central and East have maintained "Exemplary" status, while...
Will County Board Graphic.04

Undersheriff Brian Conser Retires After 29 Years of Service

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board and Sheriff’s Office honored Undersheriff Brian Conser, who is retiring after nearly three decades of service....
Screenshot 2025-12-20 at 12.18.55 PM

Frankfort Swears In New Officer, Congratulates Retiring 26-Year Veteran

Frankfort Village Board Meeting | December 15, 2025 Article Summary: The Frankfort Village Board on Monday, Dec. 15, 2025, celebrated a transition within its police force, swearing in Timothy Hoak...
summit-hill-junior-high-school-frankfort-161

District 161 to Overhaul Food Service with New Management Contract

Summit Hill School District 161 Meeting | December 17, 2025 Article Summary: The Summit Hill School District 161 Board has approved the development of a Request for Proposals (RFP) for...
Will County Board Graphic.04

County Approves Engineering for Peotone Road and Safety Upgrades

Will County Board Meeting | December 18, 2025 Article Summary: The County Board approved a Phase I engineering contract for improvements to Wilmington-Peotone Road and authorized an agreement for license...
frankfort illinois library logo graphic.1

Frankfort Library Board Accepts Audit Showing $498,000 Increase in Net Position

Frankfort Public Library District Board Meeting | Nov. 20, 2025 Article Summary: The Frankfort Public Library District Board of Trustees reviewed and accepted a clean financial audit for the fiscal...
Screenshot 2025-12-20 at 12.27.11 PM

Lincoln-Way Board Approves $731,000 Freshman Laptop Purchase

Lincoln-Way Community High School District 210 Meeting | December 18, 2025 Article Summary: The District 210 Board of Education authorized the purchase of 1,750 Lenovo laptops to equip the incoming...
Will County Board Graphic.01

Monee Solar Farm Projects Granted Extensions

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board granted six-month extensions for two special use permits related to commercial solar energy facilities in Monee...
Sufyan Farhan

Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom

Article Summary: Sufyan Farhan, 27, was arrested on December 21 following an armed robbery at a Frankfort Circle K. Deputies located the suspect hiding in a nearby McDonald's restroom after...
Screenshot 2025-12-20 at 12.15.16 PM

Village Awards $399,763 Bid for Nebraska Street Pond Dredging

Frankfort Village Board Meeting | December 15, 2025 Article Summary: The Frankfort Village Board on Monday, Dec. 15, 2025, awarded a contract to KLF Enterprises for the mechanical dredging of...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025

Will County Board Executive Committee Meeting | December 11, 2025 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, December 11, 2025, tackling a diverse agenda that included...
Planning & Zoning Graphic.4

New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space

Will County Planning and Zoning Commission Meeting | December 16, 2025 Article Summary: A New Lenox homeowner received approval to build a large pole barn that exceeds the county's size limits...
Dr. Julian Rogus School copy

District 161 Approves Emergency Boiler Replacement, Cites Past Maintenance Failures

Summit Hill School District 161 Meeting | December 17, 2025 Article Summary: The Summit Hill School District 161 Board has authorized the emergency purchase of two new boilers for Dr....
Will County Board Graphic.03

County Expands Paratransit Services, Board Members Question Long-Term Funding

Will County Board Meeting | December 18, 2025 Article Summary: The Will County Board approved an intergovernmental agreement with Pace to expand paratransit services county-wide for seniors and residents with...
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board for Dec. 10, 2025

Joliet Junior College Board Meeting | Dec. 10, 2025 Meeting Summary The Joliet Junior College Board of Trustees met on Wednesday, December 10, 2025, for a meeting marked by both...