Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

⚠️ Hydrologic Outlook issued June 20 at 3:30AM CDT by NWS Chicago IL
Today Jun 19
Sunny
78° 59°

Sunny

💨 10 to 15 mph 💧 7%

Leave a Comment





Latest News Stories

will county Committee-Capital Improvement.Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for March 3, 2026

Capital Improvements & IT Committee Meeting | March 2026 The Will County Capital Improvements and IT Committee met on Tuesday to address the county's physical and digital infrastructure. The meeting...
frankfort village hall graphic logo.8

Meeting Summary and Briefs: Frankfort Village Board for March 16, 2026

Frankfort Village Board Meeting | March 16, 2026 The Frankfort Village Board met on Monday, March 16, 2026, with Trustee Adam Borrelli presiding as Mayor Pro-Tempore in the absence of...
Screenshot

Updated: St. John Woman Charged with Nine Counts of Murder in Crete Township Triple Homicide

Article Summary: Jenna Strouble, 30, of St. John, Indiana, has been charged with nine counts of first-degree murder following the shooting deaths of her former partner, Jacob Lambert, and his...

Will County Previews ‘GuideWill’ Comprehensive Resource Management Plan

Will County Land Use & Development Committee Meeting | March 2026 Article Summary: Will County's Land Use Department unveiled the branding, interactive tools, and initial timeline for its updated Resource Management...
Will County Board Graphic.04

Will County Targets May Draft for Comprehensive Artificial Intelligence Policy

Capital Improvements & IT Committee Meeting | March 2026 Article Summary:Will County is moving closer to adopting a formal Artificial Intelligence policy, with IT staff planning to deliver a comprehensive...
frankfort village hall graphic logo.7

Frankfort Approves $150,777 Contract for Detached Storage Garage at 2 Smith Street

Frankfort Village Board Meeting | March 16, 2026 Article Summary: The Village Board awarded a bid to Algat Enterprises Group Co. Inc. to construct a new detached garage in downtown...
Will County P&Z Logo Planning Zoning.2

P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a variance to reduce a side yard setback on...
Will County Board Graphic.01

Executive Committee Advances Sweeping Overhaul of Will County Business Regulations

Will County Executive Committee Meeting | March 12, 2026 Article Summary: Will County is poised to modernize its business regulations following the Executive Committee's unanimous approval of a massive ordinance overhaul....
Will County Finance Logo

Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County has officially closed out its massive federal Emergency Rental Assistance program after distributing millions to keep nearly 2,000...
Will County P&Z Logo Planning Zoning

Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026

Will County Planning and Zoning Commission Meeting | March 3, 2026 Overall Meeting SummaryThe Will County Planning and Zoning Commission convened on Tuesday, March 3, 2026, to review a series...
will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Capital Improvements & IT Committee Meeting | March 2026 Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased...
Will County Finance Logo

Opioid Settlement Grants Funnel Nearly $600,000 to Local Police and Community Programs

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County is distributing a significant portion of its opioid settlement funds to hyper-local agencies, including the Peotone and Manhattan...
Will County Finance Logo

Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026

Will County Finance Committee Meeting | March 3, 2026 The Will County Board Finance Committee met on Tuesday to review a slate of year-end financial reports and approve routine budget...
frankfort village hall graphic logo.1

Frankfort Board Awards $551,755 in Engineering Contracts for Aberdeen Bridge Replacement

Frankfort Village Board Meeting | March 16, 2026 Article Summary: Following emergency shoring improvements, the Village Board approved structural and design engineering contracts to fully replace the Aberdeen Bridge over...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for March 10, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, March 10, 2026, to review a backlog...