Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks
Will County Finance Committee Meeting October 7, 2025
Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.
RNG Plant Performance Key Points:
-  
As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.
 -  
Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.
 -  
Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.
 -  
The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.
 
JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.
Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.
In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:
-  
Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.
 -  
A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.
 -  
Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.
 -  
Sporadic power outages caused by severe storms in late August.
 -  
Computer errors in the nitrogen control system that required the manufacturer to reprogram it.
 
Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”
Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.
Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.
“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”
Latest News Stories
 Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for July 15, 2025
 Meeting Summary and Briefs: Frankfort Square Park District for July 17, 2025
 Frankfort Fire District Faces Tighter Budget, Rising Overtime in FY 2025 Outlook
 Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event
 Frankfort Library Tables Reading Room Project Over Higher-Than-Expected Engineering Costs
 Meeting Summary and Briefs: Frankfort Township Board for July 14, 2025
 Frankfort Park District Board Approves Pay Raise for Executive Director Gina Hassett
 Meeting Summary and Briefs: Summit Hill School District 161 for July 9, 2025
 Park District’s BDC Dance Program Earns National Recognition
 Frankfort Fire District and Firefighters Union to Discuss Possible Referendum
 After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business
 Frankfort Fire Board Approves $460,000 Purchase of New Cardiac Monitors