Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for Crawford, Murphy & Tilly, Inc. to update plans to account for several new commercial and residential developments along the corridor in New Lenox and Frankfort.
Laraway Road Project Key Points:
-
Funding: The board approved $468,374 from Motor Fuel Tax funds for supplemental design services.
-
Location: The project covers a four-mile stretch of Laraway Road (CH 74) from Cedar Road to Wolf Road.
-
Reason: Original plans needed significant updates to accommodate new developments, including Camelot Homes, a Gas N Wash, a fueling center, and the Homestead Commercial strip mall.
-
Scope: The overall project will widen Laraway Road from a two-lane rural road to a five-lane divided roadway.
NEW LENOX/FRANKFORT — The massive project to widen and reconstruct Laraway Road through New Lenox and Frankfort will require nearly half a million dollars in additional design work to accommodate a boom in local development. The Will County Board on Thursday approved a $468,374 supplemental professional services agreement with the engineering firm Crawford, Murphy & Tilly, Inc.
The funding is necessary to redesign portions of the four-mile project—stretching from Cedar Road to Wolf Road—to integrate new access points and adjust for new construction that has occurred since the initial plans were developed. The overall project will transform the two-lane rural road into a five-lane, urban-style roadway with a closed drainage system.
According to the project scope, design plans needed to be updated to account for six new developments, including Camelot Homes at Spencer Road, a Gas N Wash and a fueling center at Schoolhouse Road, and the Homestead Commercial strip mall at Wolf Road.
In addition to incorporating new access points and adjusting the road’s profile, the supplemental work includes redesigning the geometry of the Wolf Road intersection, adding a mill and overlay section at the project’s west end, designing traffic signal interconnects, and planning for watermain relocations. The board unanimously approved the expenditure, which will be covered by the county’s allotment of Motor Fuel Tax funds.
Latest News Stories
Illinois law at center of normal township BDS referendum
Illinois Quick Hits: At least 7 tornadoes hit Illinois last week
Reentry housing bill draws support from advocates; debate centers on cost, public safety
Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026
On the road to 100 years: How the Forest Preserve District expanded
Illinois proposal aims to improve detection of potentially staged deaths
Bachelor’s at Illinois community colleges may widen access, affordability
Executive Committee Advances Sweeping Updates to Adult Entertainment and Wireless Facilities Ordinances
Illinois Quick Hits: Teachers union says CPS to bus students to rally
Pritzker says of BUILD Plan for homes would not cost taxpayers