Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for Crawford, Murphy & Tilly, Inc. to update plans to account for several new commercial and residential developments along the corridor in New Lenox and Frankfort.
Laraway Road Project Key Points:
-  
Funding: The board approved $468,374 from Motor Fuel Tax funds for supplemental design services.
 -  
Location: The project covers a four-mile stretch of Laraway Road (CH 74) from Cedar Road to Wolf Road.
 -  
Reason: Original plans needed significant updates to accommodate new developments, including Camelot Homes, a Gas N Wash, a fueling center, and the Homestead Commercial strip mall.
 -  
Scope: The overall project will widen Laraway Road from a two-lane rural road to a five-lane divided roadway.
 
NEW LENOX/FRANKFORT — The massive project to widen and reconstruct Laraway Road through New Lenox and Frankfort will require nearly half a million dollars in additional design work to accommodate a boom in local development. The Will County Board on Thursday approved a $468,374 supplemental professional services agreement with the engineering firm Crawford, Murphy & Tilly, Inc.
The funding is necessary to redesign portions of the four-mile project—stretching from Cedar Road to Wolf Road—to integrate new access points and adjust for new construction that has occurred since the initial plans were developed. The overall project will transform the two-lane rural road into a five-lane, urban-style roadway with a closed drainage system.
According to the project scope, design plans needed to be updated to account for six new developments, including Camelot Homes at Spencer Road, a Gas N Wash and a fueling center at Schoolhouse Road, and the Homestead Commercial strip mall at Wolf Road.
In addition to incorporating new access points and adjusting the road’s profile, the supplemental work includes redesigning the geometry of the Wolf Road intersection, adding a mill and overlay section at the project’s west end, designing traffic signal interconnects, and planning for watermain relocations. The board unanimously approved the expenditure, which will be covered by the county’s allotment of Motor Fuel Tax funds.
Latest News Stories
 Illinois quick hits: State rep. appointed circuit judge; Bailey to seek rematch with Pritzker
 WATCH: IL governor on photo with wanted suspect: ‘No way to vet everybody’
 Illinois quick hits: Constitutional amendment would guarantee parental rights
 WATCH: Republican leader: says Pritzker budget cut EO a ploy for IL tax increases
 Judge’s questions during IL gun ban arguments gives rights advocates ‘hope’
 Illinois agencies to post monthly investment reports, lawmaker calls symbolic
 Meeting Summary and Briefs: Summit Hill School District 161 for August 13, 2025
 Summit Hill 161 Accepts a Dozen Resignations, Approves New Hires
 Summit Hill 161 Approves $48K Tech Upgrade, Board Divided on New Teacher Hire
 Meeting Summary and Briefs: Frankfort Village Board for September 8, 2025
 Frankfort Resident Questions Village’s Lake Michigan Water Survey Process
 Meeting Summary and Briefs: Frankfort Public Library District for July 24, 2025