“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited “ongoing uncertainty regarding federal renewable energy policy” as a cause for delay. The extension for the Pralle Farms Partnership project on West Kennedy Road pushes its deadline to February 2026.
Peotone Solar Farm Extension Key Points:
-  
Project: A commercial solar farm by Pralle Farms Partnership on West Kennedy Road in Peotone Township.
 -  
Action: The board approved a second 180-day extension for the project’s special use permit, now valid until February 8, 2026.
 -  
Reason: The developer cited delays related to new federal renewable energy legislation, referred to as the “One Big Beautiful Bill.”
 -  
Vote: The extension was approved 19-1, with board member Katie Deane-Schlottman voting against the measure.
 
JOLIET — Citing “ongoing uncertainty regarding federal renewable energy policy,” developers of a commercial solar farm in Peotone Township were granted a second extension on their special use permit by the Will County Board on Thursday.
The project, located on a vacant property on West Kennedy Road and owned by Pralle Farms Partnership, was initially approved on March 16, 2023. Developer Trajectory Energy Partners received its first extension in February 2025.
In a memo to the board’s Land Use and Development Committee, Marguerite Kenny, a county Zoning Administrator, noted that the applicant submitted the second extension request on August 6, 2025. The request “provided a detailed letter further explaining the current federal regulation climate” following the passage of new legislation in July referred to as the “One Big Beautiful Bill.”
A building permit for the solar facility was created on March 7, 2025, but the application is still under review and awaiting required submittals, according to the memo. Special use permits typically expire after two years if construction is not lawfully established.
The board approved the second 180-day extension in a 19-1 vote, with Katie Deane-Schlottman casting the lone dissenting vote. The permit is now valid through February 8, 2026, giving the developers more time to navigate the federal policy landscape and finalize their construction permit.
Latest News Stories
 More California voters are liking Trump’s job performance
 U.S. national debt tops $37 trillion
 Illinois quick hits: Human trafficking law signed; Mercyhealth to pay for COVID vaccine discrimination
 Justice Department finds GWU in violation of Title VI
 WATCH: Nearly 400 people become U.S. citizens at Illinois State Fair
 Appeals court says Trump can move forward with foreign aid cuts
 WATCH: Governor suggests ending nuclear ban as lawmaker files pro-nuclear bill
 Kratom byproduct in gummies, candies, ice cream ruled same as herion, LSD
 ‘Liberation Day’ reignites D.C. statehood debate
 Trump to meet with Democratic leaders to discuss govt funding bills
 WATCH: Illinois Democrats blast Trump, Republicans at state fair
 Social Security’s 90th anniversary sparks debate over how to address insolvency
 Colorado ranks eighth nationally for battling antisemitism