“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited “ongoing uncertainty regarding federal renewable energy policy” as a cause for delay. The extension for the Pralle Farms Partnership project on West Kennedy Road pushes its deadline to February 2026.
Peotone Solar Farm Extension Key Points:
-
Project: A commercial solar farm by Pralle Farms Partnership on West Kennedy Road in Peotone Township.
-
Action: The board approved a second 180-day extension for the project’s special use permit, now valid until February 8, 2026.
-
Reason: The developer cited delays related to new federal renewable energy legislation, referred to as the “One Big Beautiful Bill.”
-
Vote: The extension was approved 19-1, with board member Katie Deane-Schlottman voting against the measure.
JOLIET — Citing “ongoing uncertainty regarding federal renewable energy policy,” developers of a commercial solar farm in Peotone Township were granted a second extension on their special use permit by the Will County Board on Thursday.
The project, located on a vacant property on West Kennedy Road and owned by Pralle Farms Partnership, was initially approved on March 16, 2023. Developer Trajectory Energy Partners received its first extension in February 2025.
In a memo to the board’s Land Use and Development Committee, Marguerite Kenny, a county Zoning Administrator, noted that the applicant submitted the second extension request on August 6, 2025. The request “provided a detailed letter further explaining the current federal regulation climate” following the passage of new legislation in July referred to as the “One Big Beautiful Bill.”
A building permit for the solar facility was created on March 7, 2025, but the application is still under review and awaiting required submittals, according to the memo. Special use permits typically expire after two years if construction is not lawfully established.
The board approved the second 180-day extension in a 19-1 vote, with Katie Deane-Schlottman casting the lone dissenting vote. The permit is now valid through February 8, 2026, giving the developers more time to navigate the federal policy landscape and finalize their construction permit.
Latest News Stories
Frankfort Swears In New Officer, Congratulates Retiring 26-Year Veteran
District 161 to Overhaul Food Service with New Management Contract
County Approves Engineering for Peotone Road and Safety Upgrades
Frankfort Library Board Accepts Audit Showing $498,000 Increase in Net Position
Lincoln-Way Board Approves $731,000 Freshman Laptop Purchase
Monee Solar Farm Projects Granted Extensions
Frankfort Man Arrested in Gas Station Robbery Found Hiding in McDonald’s Restroom
Village Awards $399,763 Bid for Nebraska Street Pond Dredging
Meeting Summary and Briefs: Will County Board Executive Committee for December 11, 2025
New Lenox Homeowner Granted Variance for 4,000-Square-Foot Accessory Space
District 161 Approves Emergency Boiler Replacement, Cites Past Maintenance Failures
County Expands Paratransit Services, Board Members Question Long-Term Funding