Frankfort Park Board Approves Over $19,000 in Construction Changes for Fort Frankfort Project
Article Summary: The Frankfort Park District Board of Commissioners approved a series of construction change orders for the Fort Frankfort project, resulting in a net cost increase of $19,216.50. The changes include adding safety-motivated limestone stairs and a larger concrete base for a spinner playground feature, while also realizing a cost savings from the removal of an unnecessary railing.
Frankfort Park District Key Points:
-
The board approved a net change order of $19,216.50 for the Fort Frankfort project with Schwartz Construction.
-
An additional $11,477 will be spent to install limestone stairs near a concession stand shelter to address a steep grade and improve safety.
-
A cost of $7,739.50 was added to install a larger concrete pad for an “Inclusive Orbiter Spinner” due to a change in the manufacturer’s installation requirements.
-
The district received a credit of $4,094 for removing a railing that was determined to be unnecessary for a new set of stairs.
The Frankfort Park District Board of Commissioners on Tuesday, August 12, 2025, unanimously approved construction changes for the ongoing Fort Frankfort project that will add new safety features and accommodate updated equipment specifications, resulting in a net cost increase of $19,216.50.
The board action addresses three separate modifications to the project plan with contractor Schwartz Construction. According to a report from Executive Director Gina Hassett, the most significant expense is an $11,477 addition for the installation of new limestone stairs. The stairs will be located near a shelter on the east side of the concession stand, an area with a significant grade change.
Hassett’s report explained that staff recommended the installation after observing that park visitors would likely take the most direct path, which would create a worn area on a steep slope. “If there are not stairs installed, it would be a heavily worn area and given the slope could result in a injuries,” the report stated, highlighting the change as a proactive safety measure.
A second cost increase of $7,739.50 was approved to create a large concrete pad for an “Inclusive Orbiter Spinner” from the manufacturer Burke. The original plan called for individual footings, but the installation instructions were changed by the manufacturer between the time the piece was ordered and when it was delivered. The new requirements necessitate a larger, more costly concrete base.
Offsetting some of the new expenses, the district will receive a $4,094 credit. During a construction meeting, it was determined that a planned railing for a new set of stairs connecting the park and the splash pad walkway was not needed, allowing for its removal from the project scope.
The combination of the two cost additions and the credit results in the total net increase of $19,216.50.
Commissioner Tom Barz made the motion to approve the change order, which was seconded by Commissioner Tom Ruvoli. The motion passed with a 4-0 roll call vote. Commissioners Barz, Ruvoli, Elmer Gentry, and Mark Ponton voted in favor. Commissioner Michael McCarey was absent. The meeting was led by President pro tempore Gentry.
Latest News Stories
Lincoln-Way East Cheerleaders Honored for 8th State Championship
Executive Committee Advances “Project Northwinds”: 2,475 Jobs and $346 Million Investment Proposed for Former Caterpillar, Lion Electric Sites
Land Use Committee Advances Mokena Scrap Yard and Homer Glen Landscape Business Over Local Objections
District 210 Reports Insurance Deficit Amid National Healthcare Cost Spikes; Finances Remain Stable
Planning Commission Backs 5-MW Peotone Solar Farm; Developer Pledges Pollinator Habitat and Community Funds
Joliet Junior College Board Approves $2 Tuition Increase Amidst Heated Debate Over Enrollment and Spending
Lincoln-Way Board Ratifies Three-Year Support Staff Contract with Significant Hourly Raises
Frankfort Seeks Public Vision for Downtown Urban Design
Green Garden Residents Seek Frankfort’s Support in Opposing 6,000-Acre Solar Farm
State of the College: Local Legislators Bolster Student Support Services
Meeting Summary and Briefs: Public Health & Safety Committee for February 5, 2026
State of the College: Dual Credit Program Enrollment Hits 6,000 Students
Meeting Summary and Briefs: Finance Committee for February 3, 2026
Fairmont Neighborhood Plan Update Prioritizes Infrastructure and Beautification Following Demographic Shift