WCO-Landfill-8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Spread the love

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Leave a Comment





Latest News Stories

summit-hill-junior-high-school-frankfort-161

Summit Hill 161 Board Split on Administrative Assignments, Contracts

Article Summary: The Summit Hill District 161 Board of Education showed rare division in two separate 6-1 votes to approve administrative assignments and contracts for the upcoming school year. Board member...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for August 21, 2025

The Will County Board received County Executive Jennifer Bertino-Tarrant’s proposed $791 million budget for fiscal year 2026, which holds the line on the property tax levy while funding key services....
frankfort illinois library logo graphic.1

Frankfort Library Overcharged Nearly $23,000 in Loan Payments Due to Wintrust Bank Error

Article Summary: The Frankfort Public Library District was undercharged by $22,843.40 on interest payments for a new debt certificate after Wintrust Bank used an incorrect amortization schedule for its automated...
frankfort township graphic

Frankfort Township Board Denies Liquor and Gaming Permits for Two Restaurants

Article Summary: The Frankfort Township Board of Trustees denied special use permits for Dimitri Best Food and Kismet Restaurant, both of which were seeking ancillary liquor licenses with the intent to...
summit-hill-junior-high-school-frankfort-161.2

New Hires Approved for Summit Hill District 161

Article Summary: Summit Hill School District 161 approved the hiring of several new staff members, including a District Wide Gifted and Talented Coordinator and multiple paraprofessionals and custodians. The approvals were...
frankfort-park-district

Frankfort Park District Approves $131,500 for Park Upgrades and Master Plan

Article Summary: The Frankfort Park District Board of Commissioners approved agreements totaling $131,500 with planning firm Design Perspectives to design and construct parking lots at two parks and to update master...
frankfort-square-park-district.2

Hunter Prairie Park Redevelopment Moves to Next Phase as Demolition Finishes

Article Summary: The Frankfort Square Park District’s redevelopment of Hunter Prairie Park is progressing, with the demolition phase now complete and work beginning on grading, excavation, and the layout for...
Will County Recorder Graphic.1

Will County Board Approves New Fee Schedule for Recorder of Deeds

Article Summary: The Will County Board has approved a revised fee schedule for the Recorder of Deeds office, which will take effect on October 1, 2025. The changes, based on...
frankfort fire district graphic logo.2

Frankfort Fire District Explores Tax Referendum, Moves to Hire Outreach Consultant

Article Summary: The Frankfort Fire Protection District is taking initial steps toward asking voters for a tax increase for the first time in 25 years, citing revenue challenges and the...
frankfort-school-district-161.2-e1754272831494

Summit Hill 161 Awards $115,905 Contract for Dr. Julian Rogus School Play Area

Article Summary: The Summit Hill District 161 Board of Education unanimously awarded a $115,905 construction contract to Schwartz Construction Group, Inc. for a new play area at Dr. Julian Rogus School....
frankfort fire district graphic logo.2

Frankfort Fire District to Spend $92,000 on New Cardiac Monitors

Article Summary: The Frankfort Fire Protection District Board of Trustees was scheduled to approve the purchase of six new cardiac monitors and related accessories for $91,955 from ZOLL. The acquisition is...
frankfort fire district graphic logo.2

Frankfort Fire District Reviews Tentative Budget for Fiscal Year 2025

Article Summary: The Frankfort Fire Protection District has taken the first step in its annual budgeting process with an initial review of the tentative budget for Fiscal Year 2025. District Accountant...
WCO Board Aug 21.3

Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways

Article Summary: The Will County Board unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on the nation's roadways. The...
Energy advocate applauds oil and gas commingling updates

Energy advocate applauds oil and gas commingling updates

By Tate MillerThe Center Square Oil and gas commingling rules have been updated in accordance with the Big Beautiful Bill in order to strengthen energy production and safety, with energy...
will county board meeting graphic.5

Will County Board Approves Permits for Landscaping Business and Restaurant Liquor Service in Frankfort Area

Article SummaryThe Will County Board unanimously approved three separate special use permits for businesses in the Frankfort area, allowing a landscaping operation in Green Garden Township to continue and two...