Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Article Summary:
The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
Meeting Summary and Briefs: Frankfort Park District for August 12, 2025
Frankfort Fire District Hires Two Firms for Over $70,000 to Lead Referendum Campaign
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for August 20, 2025
Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships
Frankfort Library Board Approves FY 2025-26 Budget, Transfers $300,000 to Reserve Fund
County Board Abates Over $25 Million in Property Taxes for Bond Payments
Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment
Meeting Summary and Briefs: Frankfort School District 157-C for August 12, 2025
Frankfort Square Park District Receives Clean Bill of Health in Annual Financial Audit
Frankfort Highway Department Plans Levy Increase to Replace Aging Trucks
Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Everyday Economics: Jobs, Waller and whether the Fed can thread the needle
Attack at Michigan church leaves multiple casualties