County RNG Facility Shows Strong Performance Despite Solar Challenges
Will County’s Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability.
Project manager Greg Komperda told Finance Committee members July 1 that the facility has operated at 94-95% capacity for three consecutive months, representing full operational capacity. Production has consistently exceeded both targets and minimum contractual obligations.
“We met our production targets in April, May, and June,” Komperda reported. The facility generated $5.26 million in revenue through June 20 against $3.89 million in expenses, though debt service payments result in approximately $1.2 million negative cash flow.
County Board member Julie Berkowicz questioned whether solar power could help offset electricity costs, noting the facility’s consumption of 3,500 kilowatts per hour. Dave Hartke, director of Land Use, explained that meeting those power needs would require 40-50 acres of solar panels.
“You’re probably looking at a solar farm around maybe 40 50 acres maybe around there to supply the electricity for the plant,” Hartke said. “At this point there’s no room around unless we’ve had to create a solar farm adjacent property.”
Any solar development faces complications from uncertainty about potential landfill expansion. Officials indicated they prefer to wait until expansion decisions are made before committing to permanent solar installations.
Daniel Butler noted that a complete solar installation could cost hundreds of millions of dollars, questioning the return on investment. Officials acknowledged that even partial solar power could help reduce costs but emphasized the need for careful analysis of long-term planning.
The facility successfully hosted tours in June and has improved spare parts inventory planning to reduce downtime risks. Despite minor operational challenges including utility outages and equipment repairs, the facility has maintained strong performance metrics above the 92% target runtime.
Latest News Stories
Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for July 15, 2025
Meeting Summary and Briefs: Frankfort Square Park District for July 17, 2025
Frankfort Fire District Faces Tighter Budget, Rising Overtime in FY 2025 Outlook
Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event
Frankfort Library Tables Reading Room Project Over Higher-Than-Expected Engineering Costs
Meeting Summary and Briefs: Frankfort Township Board for July 14, 2025
Frankfort Park District Board Approves Pay Raise for Executive Director Gina Hassett
Meeting Summary and Briefs: Summit Hill School District 161 for July 9, 2025
Park District’s BDC Dance Program Earns National Recognition
Frankfort Fire District and Firefighters Union to Discuss Possible Referendum
After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business
Frankfort Fire Board Approves $460,000 Purchase of New Cardiac Monitors