County RNG Facility Shows Strong Performance Despite Solar Challenges
Will County’s Renewable Natural Gas facility is exceeding production targets while officials explore options to reduce substantial electricity costs that currently impact profitability.
Project manager Greg Komperda told Finance Committee members July 1 that the facility has operated at 94-95% capacity for three consecutive months, representing full operational capacity. Production has consistently exceeded both targets and minimum contractual obligations.
“We met our production targets in April, May, and June,” Komperda reported. The facility generated $5.26 million in revenue through June 20 against $3.89 million in expenses, though debt service payments result in approximately $1.2 million negative cash flow.
County Board member Julie Berkowicz questioned whether solar power could help offset electricity costs, noting the facility’s consumption of 3,500 kilowatts per hour. Dave Hartke, director of Land Use, explained that meeting those power needs would require 40-50 acres of solar panels.
“You’re probably looking at a solar farm around maybe 40 50 acres maybe around there to supply the electricity for the plant,” Hartke said. “At this point there’s no room around unless we’ve had to create a solar farm adjacent property.”
Any solar development faces complications from uncertainty about potential landfill expansion. Officials indicated they prefer to wait until expansion decisions are made before committing to permanent solar installations.
Daniel Butler noted that a complete solar installation could cost hundreds of millions of dollars, questioning the return on investment. Officials acknowledged that even partial solar power could help reduce costs but emphasized the need for careful analysis of long-term planning.
The facility successfully hosted tours in June and has improved spare parts inventory planning to reduce downtime risks. Despite minor operational challenges including utility outages and equipment repairs, the facility has maintained strong performance metrics above the 92% target runtime.
Latest News Stories
Meeting Summary and Briefs: Frankfort Fire Protection District Board of Trustees for August 19, 2025
Frankfort Library Approves Funds for New Heaters, Tree Removal
Summit Hill 161 Welcomes Will County Sheriff’s Deputy as New School Resource Officer
Meeting Summary and Briefs: Frankfort Square Park District for August 21, 2025
Frankfort Fire Board Adopts FY 2026 Budget Amid Rising Insurance Costs
Meeting Summary and Briefs: Will County Board for September 18, 2025
Library Approves $14,700 for Reading Room Architectural Services
Meeting Summary and Briefs: Frankfort Township Board for August 11, 2025
Summit Hill 161 Board Approves $40 Million Budget for 2025-2026 School Year
Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025
LWSRA Details Services for Residents with Disabilities, Plans ‘Hero Village’ Grand Opening
JJC Moves Forward with Major Technology Overhaul to Modernize College Operations
Meeting Summary and Briefs: Frankfort Park District for August 12, 2025