 Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
 
 Illinois treasurer promises to pass nonprofit legislation vetoed by Pritzker
 
 Regional Office of Education Highlights School Safety, New Learning Programs in Update
 
 Fort Frankfort Playground Grand Opening Delayed Until Spring 2026
 
 Lincoln-Way to Purchase New Buses, Add Smaller Vehicles to Address Driver Shortage
 
 Will County Awards $10.4 Million Contract for Bell Road Widening Project
 
 Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit
 
 Summit Hill 161 Board Approves Longevity Pay Bumps for Non-Certified Staff
 
 Meeting Summary and Briefs: Village of Frankfort Board for October 6, 2025
 
 Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate
 
 Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year
 
 Frankfort Township Board Denies Permit for New Bar on St. Francis Road
 
 Summit Hill 161 Explores Switch to MacBooks for Teachers, Plans Pilot Program
 
  
 