Louisiana joins four states in complaint against electricity grid operator

Louisiana joins four states in complaint against electricity grid operator

Spread the love

(The Center Square) – Louisiana and four other state public service commissions have filed a formal complaint against the Midcontinent Independent System Operator, accusing the grid operator of reliance on “patently unreasonable” assumptions to justify $22 billion worth of transmission projects in its long-range planning portfolio.

The grid operator functions to coordinate the reliable transmission of electricity across multiple states by managing power flows.

In a filing with the Federal Energy Regulatory Commission, the Louisiana Public Service Commission joined commissions from Arkansas, Mississippi, North Dakota and Montana in an accusation of a defective business case for the nonprofit’s Long Range Transmission projects known as Tranche 2.1.

Tranche 2.1, which only includes grid upgrades in the Midwest, will construct “a 3,631-mile 765 kV and 345 kV backbone that ensures future reliability while providing benefits that exceed costs,” according to the grid operator.

“The Louisiana Public Service Commission joined the complaint for two major reasons,” a spokesman for the commission wrote to The Center Square in an email. “First, MISO’s LRTP 2.1 process is flawed due to the unreasonable underlying assumptions relied upon to justify those projects as Multi Value Projects, which results in a broad allocation of costs. In addition, our concern is that, although currently there is no allocation of these costs to Louisiana, due to FERC precedent established in the Sunflower case, Louisiana is not guaranteed insulation from an allocation of those costs into the future.”

“These projects fail to meet the fundamental requirement of providing benefits equal to or in excess of forecasted costs,” the complaint says.

The complaint says the grid operator overstated economic benefits to push the portfolio’s benefit-to-cost ratio above the 1.0 threshold that is required.

The complaint asserts that the grid operator added new benefit metrics and revised others after its original modeling failed to show benefits exceeding costs. Stakeholders, including Midcontinent’s Independent Market Monitor, reportedly raised concerns about these assumptions throughout the stakeholder process, but the complaint says those were “ignored.”

“When the market monitor identified major defects with MISO’s assumptions, rather than address those concerns, MISO ordered staff to challenge the IMM’s authority,” the complaint states.

Potomac Economics, the market monitor, says the plan likely looks better on paper than in reality.

Potomac said Midcontinent made a couple of assumptions that don’t hold water, such as counting extra power plants that wouldn’t actually be needed and exaggerating the risk of blackouts, among others. Fixing those mistakes, the complaint argues, would show the plan’s costs outweigh its benefits.

Midcontinent, operating across parts of 15 states and the Canadian province of Manitoba, pushed back strongly against the allegations. The grid operator said the “deficient and misleading” complaint threatens to undermine needed infrastructure and inject regulatory uncertainty into future generation and transmission planning.

Jeremiah Doner, representing the grid operator, rejected the claim that Tranche 2.1 forces states to pay for unneeded projects, saying the plan was built in collaboration with state regulators and utilities and reflects their resource plans.

Doner said in his testimony that 93% of the generation in its “1A” planned infrastructure upgrades and more than half in “2A” came directly from member-submitted plans, with the rest added by the operator’s model to meet system needs.

“While the LRTP Tranche 2.1 Portfolio is estimated to cost MISO members about $5 per 1 MWh or 1,000 kWh of energy used, that investment will 12 provide $10 to $18 of value over that same amount of usage,” Midcontinent Independent System Operator said.

The long term planning effort is being rolled out in multiple tranches, with the first three focused on the Midwest region. Later tranches will address the South region and interconnections between the Midwest and South, where the nonprofit says transmission capacity is increasingly strained by a surge in renewable projects seeking interconnection.

The company’s South region includes Louisiana, Texas, Mississippi and Arkansas. The Central includes Illinois, Missouri, Kentucky, Indiana, Michigan and Wisconsin. The North includes Iowa, Minnesota, South Dakota, North Dakota, Montana and the Canadian province of Manitoba.

Leave a Comment





Latest News Stories

will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
frankfort village hall graphic logo.1

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
frankfort village hall graphic logo.8

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
frankfort illinois library logo graphic.5

Frankfort Library Board Reorganizes with New Officers, Seeks to Fill Vacancy

The Frankfort Public Library District Board of Trustees underwent a significant transformation Thursday night, swearing in five new members, electing a new slate of officers, and announcing an immediate search...
frankfort illinois library logo graphic.1

Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000

The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of...
Meeting-Briefs

Meeting Summary: Frankfort Public Library District for May 22, 2025

The Frankfort Public Library District Board of Trustees held its reorganization meeting on Thursday, welcoming five new members and electing new officers. The board also received an update on the...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
Frankfort-Township-Logo-Graphic

Golf Carts Not Permitted on Township Roads, Supervisor Clarifies

Residents hoping to drive golf carts on roads in unincorporated Frankfort Township are out of luck, as the practice is illegal under state law, Supervisor Nick George clarified at the...