Exec Cmte 8.14.25.4

Executive Committee Details Spending of $134 Million in Pandemic Relief Funds

Article Summary: Will County has expended 61% of its $134 million in federal American Rescue Plan Act (ARPA) funds, with significant investments made in infrastructure, health, and economic development. Officials reported that over $81.2 million has been spent, with the remaining balance to be fully allocated by the end of 2026.

ARPA Program Key Points:

  • Over $81.2 million of the $134 million total award has been spent as of June 30, 2025.

  • Infrastructure projects account for the largest allocation at $47.5 million, with 31% expended so far due to ongoing construction.

  • Funds have supported over 200 subrecipients, including municipalities, non-profits, and park and library districts.

  • All funds must be fully expended by the federal deadline of December 31, 2026.

JOLIET, IL – Will County has spent just over 61% of its $134 million federal pandemic relief allocation, with a little over a year and a half remaining before the program’s spending deadline, officials reported to the County Board Executive Committee on Thursday.

Anna Sitton of Accenture, the firm managing the county’s ARPA program, presented an annual update showing that $81.2 million had been expended as of June 30, 2025. The funds, authorized under the American Rescue Plan Act of 2021, have been distributed across more than 200 subrecipients, including local governments, non-profits, and special districts, through a framework of six pillars established by the county.

The largest portion of the funding, $47.5 million, was allocated to infrastructure. Sitton noted that the 31% expenditure rate in this category is expected to rise sharply, as many capital projects are still underway. “We’re anticipating that 60% of all infrastructure projects will be complete by the end of this year,” Sitton said, adding that an “influx of spending” would be reflected in reports for the final two quarters of 2025.

Recent completions include the Tinley Park Post 13 Lift Station project, which installed a new control system and backup generator to ensure reliable sewer service, and work by the Manhattan Fire Department to establish water and sewer infrastructure for its new safety complex.

Other pillars show higher expenditure rates. The Revenue Replacement category is 92% spent, while Economic Development and Unmet Needs are at 84% and 87%, respectively. The $6.16 million Administration pillar, which includes the cost of managing the program, is 82% spent. Sitton confirmed for board members that the allocated administration amount is the final topline number.

The Health pillar, at 57% expended, funds ongoing staffing and operations for healthcare partners, resulting in a “steady tick up of expenditures on a month-to-month basis,” Sitton explained. Highlights from this category include Silver Cross Hospital expending its full $737,500 award to help renovate its new healthcare facility in Crest Hill, which opened in June. The United Way of Will County’s MAPP Food for All Program, which supports five partners to combat food insecurity, has a remaining balance of about $173,000 from its original $779,805 allocation.

During questions, board member Judy Ogalla inquired about the “Heroes” scholarship program, which dedicated $10 million to be split between Joliet Junior College, University of St. Francis, Lewis University, and Governors State University. The funds provide scholarships of up to $5,000 per year for students pursuing degrees in healthcare and education.

“JJC has expended their funds, so they have successfully completed their program, and we’re working with the four-year institutions on expenditure through the end of 2026,” Sitton reported, offering to provide a detailed breakdown of student participation numbers to the board.

The final deadline for all ARPA funds to be expended is December 31, 2026, with a final report due to the federal government in April 2027.

Events

26 Aug
28 Aug
28 Aug
29 Aug
30 Aug
30 Aug 25
30 Aug
30 Aug 25

Latest News Stories

will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
frankfort village hall graphic logo.1

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
frankfort village hall graphic logo.8

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting-Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
frankfort illinois library logo graphic.5

Frankfort Library Board Reorganizes with New Officers, Seeks to Fill Vacancy

The Frankfort Public Library District Board of Trustees underwent a significant transformation Thursday night, swearing in five new members, electing a new slate of officers, and announcing an immediate search...
frankfort illinois library logo graphic.1

Frankfort Library HVAC Project Nears Completion, Cost Estimated Up to $260,000

The Frankfort Public Library’s major HVAC replacement project is nearly complete, with the new system officially turned on this week, according to an update provided at the Library Board of...
Meeting-Briefs

Meeting Summary: Frankfort Public Library District for May 22, 2025

The Frankfort Public Library District Board of Trustees held its reorganization meeting on Thursday, welcoming five new members and electing new officers. The board also received an update on the...
Frankfort-Township-Logo-Graphic

Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects

Frankfort Township employees will receive a 2.5% cost-of-living pay increase after the Board of Trustees unanimously approved the adjustment at its Monday, May 19 meeting. The move came as Supervisor...
Frankfort-Township-Logo-Graphic

New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board

A new bar focused on high-end liquor and an extensive wine collection is one step closer to opening in Frankfort Township after the Board of Trustees voted to recommend a...
Frankfort-Township-Logo-Graphic

Golf Carts Not Permitted on Township Roads, Supervisor Clarifies

Residents hoping to drive golf carts on roads in unincorporated Frankfort Township are out of luck, as the practice is illegal under state law, Supervisor Nick George clarified at the...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for May 19, 2025

The Frankfort Township Board approved a 2.5% cost-of-living raise for its employees and discussed several major projects at its meeting on Monday, May 19. Supervisor Nick George announced that the...
Screenshot-2025-06-16-at-3.26.08-PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will-county-board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...